Open
What do programme sunsets, option preservation and licence reapplication cost and take in practice?
Research High
governancelicensingsunsetreal-options
Background
The owner has ruled that the month-180 sunset acts automatically (G-1.6) and that a failed licence gate allows one bounded reapplication (G-1.3). Still open:
- At M180 (rq-0-69). Claude: authority expires, no extension in place, re-entry only by a new decision. GPT: authority expires, but bounded replacement authority is allowed for preservation work. Gemini: fallback executes, with an owner-level clock pause for catastrophic external shocks.
- The planning buffer.
- The recovery window after licence failure (rq-0-70): 6, 12 or 18 months.
- Eligible failures and redesign scope.
The models disagree mostly on what preserving an option and reapplying for a licence actually cost and take, which no one supplied.
Feeds decision-sheet items 2.9, 2.10 and 2.11 and the buffer item; the buffer also depends on rq-0-63 (integrated schedule).
Why This Matters
Pre-committed termination protects against sunk-cost drift, but only if keeping the option alive and restarting are priced. A licence window that is shorter than regulators' actual review times just means failing a second time.
How this gets answered
- Literature — Restart and mothballing costs for shut-down capabilities (e.g. Pu-238 production restart, production-line shutdowns with tooling preservation); sunset clauses in programmes and how often they held; review and reapplication timelines for novel-activity licences (space-resources authorisation regimes, launch and re-entry licensing, nuclear and mining permits as analogues).
- Stakeholder — Licensing authorities on realistic review cycles and what counts as a remediable deficiency (outreach draft: Luxembourg Space Agency oq-14-1). The US authority for novel in-space activities must first be identified.
Research Directions
- Restart cost and time as a fraction of the original programme, with how much was preserved.
- Licence review and reapplication durations, and the share of reapplications that succeeded.
- How often sunset clauses were extended in place, and what followed.
Owner decides afterwards: whether an extension in place is ever allowed, and the cap on preservation spending.
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Organizational Infrastructure
- Question ID
- rq-0-83
- Created
- 2026-10-20
- Related BOM Items
- bom-0-7
Related Questions
Governance structure for multi-century, volunteer-driven global coordination
critical - open
Post-scarcity economic valuation frameworks for self-replicating systems
medium - open
Integrated schedule for Phase 0A, the gates and the 0B ramp
high - investigating
What should the TRL rating of deep-space communications and command (T26) assess?
high - answered
Which risk class should apply to the eight technologies the panel split on (T02, T10, T14, T15, T22, T24, T25, T26)?
high - investigating