Project Dyson — Technical Document

Phase 0 Technical Feasibility Assessment

Asteroid resources for the swarm: research, pathfinders and a gated production option

Version 2.0 Readiness assessed 2026-10-17 Panel: Claude Opus 5.5, Gemini 3.1 Pro, GPT-6.1 Sol
1.

Executive Summary

Phase 0 asks whether material from near-Earth asteroids can supply the swarm. A three-model re-assessment found the earlier plan, a central station processing ore at scale, could not close. The agreed course is decision D-01 (accepted 2026-10-12): Fund 0A. Hold 0B as a gated real option, sized at the gate by signed Phase 1 demand. Call Phase 0 a capability programme, not a cost saving.

This report rests on 26 critical technologies rated on TRL and AD², 11 decision gates under D-02, and 87 Phase 0 research questions. It quotes no single cost: the panel's Phase 0 estimates differ by up to an order of magnitude, and they are shown side by side below.

TRL 2–5
Current readiness, all 26 technologies
17
Project-ending technologies
11
Gates (2 KDPs, 4 discriminating)
14
Gate criteria awaiting a ruling

Readiness: early. No critical technology is above TRL 5; KDP-0B requires TRL 6 with no waivers for the project-ending ones. The panel estimates 1–15 years to reach target, depending on the technology. That is why 0B is an option, not a commitment.

Hardest project-ending technologies

  1. T04 Asteroid excavation (with anchoring per Gemini and GPT)
    TRL 2–3 → 6 · AD² 6–7 · 5–15 yr
  2. T08 Particle containment, escape verification and tailings management
    TRL 2–3 → 6 · AD² 6–7 · 4–10 yr
  3. T16 Anchoring, hold-down and surface mobility on low-cohesion bodies
    TRL 2–4 → 6 · AD² 7 · 4–14 yr

Closest to target

  1. T03 MW-class waste-heat rejection (plant and tug)
    TRL 2–5 → 6 · Project Ending
  2. T20 Distributed energy storage (GPT: and microgrid power management)
    TRL 3–5 → 6 · Architecture Change
  3. T24 Dust-tolerant long-life mechanisms and seals
    TRL 2–5 → 6 · Project Ending

Recommendation

D-01: Fund 0A. Hold 0B as a gated real option, sized at the gate by signed Phase 1 demand. Call Phase 0 a capability programme, not a cost saving. D-02: Hybrid: NASA life-cycle gates with TRL/AD² for each critical technology, plus four discriminating gates (target, demand, economics, licence). Stringency follows reversibility.

Still proposed, used as interim positions: D-03 (escaped-debris and containment limit); D-04 (where phase 0 delivers its product); D-05 (tug propellant; water-ep track).

2.

Phase 0 Architecture

All three models agreed the changes below. Where they gave different numbers, the range spans them; contested values stay with the model that gave them.

ChangeValueAttribution
Split Phase 0 into 0A (research + pathfinders) and gated 0B (industrial)Structure agreed; budgets → §3All three
Abandon 50 kt/yr central SEL4/L5 ore processing—All three
Co-locate at least beneficiation and primary processing at the target NEA; ship product, not oreReference architectureAll three. GPT: "favoured but not universally optimal". Claude retains a central station fed with ≥20:1 concentrate as an alternative. Gemini's own weighted QOC scores SEL1 marginally higher (see §6).
Narrow product to native/reduced Fe-Ni; defer solar-grade Si and oxide-derived Al/SiFe-Ni baseline; Al/Si pilot or deferredAll three
Delivered product scale of order 1 kt/yr0.6–2.5 kt/yrClaude 0.6–2.2 (central 1.3); Gemini 1.0–2.5 (1.5, of which 0.3 is water); GPT 0.6–1.0 contracted (0.67–1.33 capacity)
MW-class cargo tugs1.0–2.5 MWe each; 10–18 tugs; 150–300 t payload→ §3 for point values
Robots powered by HV tether from site power, with onboard battery for mobility and safe-mode1–3 kV; battery 10–50 kWhClaude 2–3 kV, 10–30 kWh; Gemini 1–3 kV, 15–25 kWh; GPT 20–50 kWh, voltage unspecified
Delete the 200–500 MWh Li-ion line; size storage per site0.5–15 MWh totalClaude 0.5–3 MWh + thermal; GPT 1.3–3.3 MWh; Gemini <15 MWh (YAML 10 MWh)
Reject $5/W array pricingHardware ~$30–150/W, launch separately accountedClaude $30–150/W hardware ($50–230 installed incl. launch); Gemini $60–100/W (spec $75, range $50–110); GPT $30–100/W allowance ($45–220 with delivery)
Replace 32–50 × 100 kg monoprop prospectorsRemote survey + 4–10 EP rendezvous scouts of 200–600 kgAll three agree a monoprop bus has ~0.5–0.8 km/s Δv. Remote-survey method differs (→ §3).
Add an Earth-to-space launch/delivery lineLine agreed; magnitude → §3All three
Add a comms, ground segment and mission-operations line; DSN not assumed freeLine agreedAll three. Claude and GPT reject the round-1 2.5 TB/day (~230 Mbps) figure.
Phase 0 uncrewed; remove habitat and quarterly visits0 crew visitsAll three. Claude and GPT reject the "human-rating" label in favour of structural reserve plus docking/servicing interfaces. Gemini keeps docking ports and structural margins without commenting on the label.
Add an EP propellant supply line; xenon not baselinedLine agreed; demand → §3All three
No production LOX/LH₂ in Phase 0—All three. Claude and GPT remove the EML1 depot; Gemini "defers" cryo depots to 0B/Phase 1.
Add NRE, pathfinder, spares and contingency linesLines agreed; values → §3All three
Write a full organization (bom-0-7) specification~$100–350MClaude $100–300M; Gemini $150–250M (text $200M); GPT $150–350M
Add a debris/contamination requirement and budget tighter than 99%$50–300MThreshold → §3
Freeze one configuration-controlled baseline; mark legacy documents superseded—All three
Earth-supplied material as a fallback if microgravity metallurgy fails—All three. Ranking relative to lunar → §3.
Tie Phase 0 output to Phase 1 demand with a material/purity/date specification—All three
Add waste-heat rejection (radiators) explicitlyItem agreed; sizing → §3All three

Phase cost, as each model estimated it

Model0A0BTotal
Claude$5–15B$17–68B$22–83B (central ~40); the headline says 22–85
Gemini$3.5–5.0B (Y-statement: $3.8B)$20–35B (Y-statement: $18.5B)~$22B+
GPT$7–16B$23–175B$30–195B (central 80)

Source: reconciliation/phase-0/round-2/reconciliation/phase.md §2 and §3.17. These are the round-2 estimates, before the BOM was regenerated; they are kept as the models gave them.

Phase 0 BOM, regenerated

17 items in the structure the owner accepted on 2026-10-20, with quantities and costs from new per-item specs and consensus (Claude Opus 5.5, Gemini 3.1 Pro, GPT-6.1 Sol; 2026-10-20). Each cell is the consensus envelope; launch is in its own line, and contingency is computed from the bom-0-17 rates. Where models disagree, each position is kept on the item's page.

ItemQuantity0A (committed)0B (gated option)
Prospecting Survey and Rendezvous Scouts bom-0-16 scouts (4–8)$500M–$900M$0–$150M
Mining Robots bom-0-212 robots (2 + 10–12)$90M–$245M$280M–$825M
Processing Plant at the Target NEA bom-0-31 plant (3 trains (N = 2–6))$80M–$200M$4.5B–$9B
MW-class Cargo Tugs bom-0-414 tugs (10–18)$40M–$90M$3B–$10B
Site Power, Arrays and Storage bom-0-54 MW BOL (2–8 MW)$10M–$25M$300M–$1.8B
Water Pilot (C-type target only) bom-0-61 pilot (0–1)$15M–$45M$0–$315M(C-type target only)
Organizational Infrastructure bom-0-71 organization$30M–$100M$34M–$46M
Earth-to-Space Launch and Delivery bom-0-83 kt delivered (1.3–6 kt)$250M–$900M$3B–$16B
Communications and Ground Segment bom-0-98,000 antenna-h/yr (8,000–14,000 h/yr in 0B)$60M–$170M$130M–$440M
Mission Operations bom-0-10230 FTE peak (80–125 (0A), 180–230 (0B))$190M–$300M$450M–$700M
NRE, Ground R&D and Qualification bom-0-111 programme$3.9B–$6.6B$2.1B–$4.5B
0A Pathfinder Demonstrator bom-0-121 mission$1B–$2.5B—
Phase 1 Receiving Node (SEL1) bom-0-131 node (0–1)$5M–$15M$160M–$550M
Spares and Replacements bom-0-141 programme$20M–$45M$650M–$1.6B
Debris and Contamination Control bom-0-151 programme$45M–$80M$75M–$145M
Electric-Propulsion Propellant Supply bom-0-16300 t/yr iodine (230–400 t/yr)$20M–$60M$320M–$1.8B
Contingency and Reserve bom-0-170A 40–50%, 0B 55–70% of base$2.5B–$6.1B$8.2B–$33B
Total with contingency$8.8B–$18B$23B–$81B

Sources: reconciliation/phase-0/bom-structure.yaml, reconciliation/phase-0/bom-numbers.yaml. Totals add envelope ends (lows with lows, highs with highs), so the full range is wider than any likely outcome. 0A and 0B together: $32B–$100B. See cost reconciliation.

3.

Critical Technologies

The 17 technologies whose failure would end the production option. Each must reach TRL 6 in a relevant environment before KDP-0B. Each card is summarised from the TRL dashboard, which has every model's rating, the evidence register and the development path.

TRL 2–3 → 6 · AD² 6–7 · 5–15 years · needed in 0B

Panel envelope TRL 2–3 (Claude 2–3, Gemini 2–3, GPT 2–3). Not yet met (Claude): TRL 3: no experimental results validating predicted excavation force/torque and anchor holding capacity for cutting and capturing regolith while reacting kN-class loads at low confining stress (predictions disagree ~10x); TRL 4 additionally lacks a documented relevant-environment definition for the S/LL/M-type target class

TRL 2–3 → 6 · AD² 6–7 · 4–10 years · needed in 0B

Panel envelope TRL 2–3 (Claude 2–3, Gemini 2–3, GPT 2). Not yet met (GPT): TRL 3: documented experimental or test-validated analytical results establishing the integrated architecture's key containment, escape-measurement, contamination and tailings parameters, including credible abnormal events

TRL 2–4 → 6 · AD² 7 · 4–14 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–3, Gemini 3–4, GPT 2–3). Not yet met (Claude): TRL 3 (rubble-pile, mobility, tailings): no experimental results validating predicted anchor capacity or retention in Pa-cohesion or cohesion-scaled media. TRL 4 (monolith): no documented relevant-environment definition and no kN-class breadboard test vs prediction.

TRL 2–3 → 6 · AD² 6–7 · 4–12 years · needed in 0B

Panel envelope TRL 2–3 (Claude 2–3, Gemini 2–3, GPT 2–3). Not yet met (Claude): TRL 3 overall: no documented experimental results validating predicted feeder flow, bridging/plug onset, wall build-up, or forced-discharge mill throughput for cohesive charged regolith without body force; TRL 4 additionally lacks a documented relevant-environment definition (Bond number, charge, PSD, clast fraction by target type)

TRL 2–4 → 8 · AD² 5–6 · 4–10 years · needed in 0A

Panel envelope TRL 2–4 (Claude 3–4, Gemini 3–4, GPT 2–3). Not yet met (GPT): TRL 4: documented laboratory test performance of the selected integrated subsurface sampling, containment and grade-measurement breadboard agreeing with predictions, with the relevant environment defined

✓ G-1.5 ⧗ RQ-0-66 ← evidence RQ-0-77
TRL 2–4 → 8 · AD² 6 · 3–12 years · needed in 0A

Panel envelope TRL 2–4 (Claude 3–4, Gemini 3–4, GPT 2–3). Not yet met (GPT): TRL 4 lacks documented integrated breadboard performance agreeing with predictions for depth-resolved sampling, preparation, representative assay and route-specific recoverable-grade estimation, with the relevant environment defined; upper-bound TRL 3 also requires a documented heritage applicability argument.

✓ G-1.5 ⧗ RQ-0-66 ← evidence RQ-0-80⧗ RQ-0-73 ← evidence RQ-0-80
TRL 2–4 → 6 · AD² 6 · 6–12 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–4, Gemini 2–3, GPT 2–3). Not yet met (Gemini): Documented test performance agreeing with analytical predictions for 100+ kW operation on iodine/argon and validated 20,000+ hour life

⧗ RQ-0-75 ← evidence RQ-0-79,RQ-0-78
TRL 2–5 → 6 · AD² 5–6 · 3–10 years · needed in 0B

Panel envelope TRL 2–5 (Claude 3–4, Gemini 3–5, GPT 2–4). Not yet met (Claude): TRL 4 — no lab breadboard of a route-specific plant rejection chain (panels plus condensing HX, or rotary joint for P-RS) with documented performance agreeing with prediction, and no documented definition of the NEA relevant environment (dust, charging, IR view, local debris)

TRL 2–4 → 6 · AD² 5–6 · 3–12 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–3, Gemini 3–4, GPT 2–3). Not yet met (Claude): TRL 3: documented experimental results validating predicted grade, recovery and liberation on representative chondritic feed with realistic metal attachment; TRL 4: lab breadboard (comminution + feed + magnetic stage) meeting predictions plus documented definition of the microgravity/vacuum/charging/abrasion environment

TRL 2–4 → 6 · AD² 6 · 4–12 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–3, Gemini 3–4, GPT 3–4). Not yet met (Claude): TRL 4 - no documented definition of the relevant environment (fault catalogue, per-target conjunction duration, regolith-mechanics envelope), and no integrated or breadboard autonomy stack tested in a lab with performance agreeing with analytical predictions. A clean TRL 3 also lacks experimental validation of T10-specific key parameters (e.g., void/boulder detection latency in low-gravity analogues, plant FDIR fault coverage).

⧗ RQ-0-65 ← evidence RQ-0-77
TRL 2–4 → 6 · AD² 5–6 · 4–12 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–4, Gemini 2–3, GPT 2–3). Not yet met (Gemini): Documented test performance agreeing with analytical predictions for a component/breadboard in a laboratory environment at the required kg/h feed scale.

⧗ RQ-0-65 ← evidence RQ-0-77
TRL 2–3 → 6 · AD² 5–6 · 5–10 years · needed in 0B

Panel envelope TRL 2–3 (Claude 2–3, Gemini 2–3, GPT 2–3). Not yet met (Claude): TRL 3: no documented analytical/experimental results validating predictions of key parameters for the selected configuration in the NEA environment (dust/ejecta flux on arrays, high area-to-mass station-keeping or regolith anchoring, kV arcing/insulation life in regolith plasma sheath, day/night storage vs load); configuration not yet selected

⧗ RQ-0-65 ← evidence RQ-0-77
TRL 2–4 → 6 · AD² 6 · 4–12 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–3, Gemini 3–4, GPT 2–3). Not yet met (Claude): TRL 3 - documented analytical or experimental results validating predictions of key parameters: wear life and intervention rate of regolith-contacting parts in vacuum with asteroid simulant; dust-tolerant exchange-interface reliability after long dwell; HV tether insulation wear and arc thresholds

TRL 2–4 → 6 · AD² 5–6 · 4–10 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–4, Gemini 2–3, GPT 2). Not yet met (GPT): TRL 3: documented analytical or experimental results validating key parameters of an architecture-specific representative-feed consolidation, qualification and packaging chain

⧗ RQ-0-65 ← evidence RQ-0-77
TRL 2–5 → 6 · AD² 5–6 · 2–9 years · needed in 0B · panel diverges

Panel envelope TRL 2–5 (Claude 2–4, Gemini 4–5, GPT 3–4). Not yet met (Claude): TRL 4: documented lab test performance of the actual mechanism classes over a meaningful fraction of life agreeing with wear/leak predictions, plus a documented definition of the relevant environment (no validated metal-bearing NEA simulant, charging state or excavation-dust environment exists)

⧗ RQ-0-65 ← evidence RQ-0-77
TRL 2–4 → 6 · AD² 4–6 · 4–9 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–3, Gemini 3–4, GPT 2–3). Not yet met (Claude): TRL 3: no documented analytical/experimental results validating predicted key parameters (capture envelope, contact momentum/loads, abort and passive-safety dV under ~1e-4 m/s2 authority, array-control interaction, proximity propellant, debris collision probability) at 200-450 t stack scale; TRL 4 additionally blocked because the relevant environment (node structure, SEL1 orbit, traffic, debris source term) is undefined

⧗ RQ-0-65 ← evidence RQ-0-77
TRL 2–4 → 6 · AD² 5 · 4–10 years · needed in 0B

Panel envelope TRL 2–4 (Claude 2–4, Gemini 3–4, GPT 2–3). Not yet met (GPT): From TRL 2: architecture-specific experimental or test-validated analytical proof of key parameters; from conditional TRL 3: laboratory component/breadboard performance agreeing with predictions and a documented relevant environment

⧗ RQ-0-65 ← evidence RQ-0-77
4.

Technology Readiness Summary

Current TRL (lower bound)

1
24
2
2
3
4
5
6
7
8
9

AD² (upper bound)

1
2
3
1
4
2
5
17
6
6
7
8
9

By technology thread

ISRU & Materials Processing: 8Propulsion & Transport: 4Mining & Excavation: 6Power & Energy Systems: 5Asteroid Prospecting & Targeting: 2Governance & Programme Integration: 1

Panel agreement: 24 agree, 1 diverge, 1 set by owner ruling. 3 technologies are needed in 0A, 23 only for 0B.

5.

Decision Gates

Under D-02, gates are programme decisions (KDPs), internal reviews, and discriminating gates that test what TRL cannot. Months are windows from the start of Phase 0. 5 earlier gates were retired; the decision-gates page shows why, with every criterion.

GateTypeWindowCriteria
KDP-0A — authorise bounded Phase 0AProgramme decision (KDP)M0–36· ⧗ 1 pending
Rendezvous scout PDRReviewM12–243
0A mid-term reviewReviewM24–608· ⧗ 1 pending
Configuration-specific scout launch releaseReviewM48–1082· ⧗ 1 pending
Target gate — sampled recoverable Fe-NiDiscriminating gateM48–1804· ⧗ 3 pending
Demand gate — signed Phase 1 scheduleDiscriminating gateM48–1803· ⧗ 2 pending
Licence gate — debris, tailings and operating envelopeDiscriminating gateM48–1803· ⧗ 1 pending
Economics gate — delivered cost vs Earth supplyDiscriminating gateM60–1803· ⧗ 1 pending
KDP-0B — exercise the 0B optionProgramme decision (KDP)M72–1808· ⧗ 4 pending
Optional C-type water-pilot releaseReviewM72–1801
Pathfinder results reviewReviewM84–1442

8 gate rulings are confirmed. The rest wait on evidence from rq-0-76, rq-0-77, rq-0-78, rq-0-79, rq-0-80, rq-0-81, rq-0-82, rq-0-83.

6.

Risk Register

Ordered by consequence, then difficulty (AD²), then TRL gap. ⧗ marks a risk class or criterion awaiting an owner ruling.

TechnologyConsequenceTRLAD²Years
T04 Asteroid excavation (with anchoring per Gemini and GPT)Project Ending2–3 → 66–75–15
T08 Particle containment, escape verification and tailings managementProject Ending2–3 → 66–74–10
T16 Anchoring, hold-down and surface mobility on low-cohesion bodiesProject Ending2–4 → 674–14
T19 Microgravity bulk-solids handling (Claude: and comminution)Project Ending2–3 → 66–74–12
T11 Rendezvous scout spacecraft (with sampling per Gemini and GPT)⧗Project Ending2–4 → 85–64–10
T18 Subsurface sampling and in-situ bulk grade assay⧗Project Ending2–4 → 863–12
T01 MW-class SEP thruster and PPU cluster⧗Project Ending2–4 → 666–12
T03 MW-class waste-heat rejection (plant and tug)Project Ending2–5 → 65–63–10
T05 Microgravity beneficiation of native Fe-NiProject Ending2–4 → 65–63–12
T10 Long-duration autonomy for mining, processing and proximity operations⧗Project Ending2–4 → 664–12
T14 Propellant storage and feed at hundreds of tonnes per tug⧗Project Ending2–4 → 65–64–12
T15 Site power generation and transfer⧗Project Ending2–3 → 65–65–10
T21 Robotic maintenance, repair and spares logistics (GPT: and site installation and recovery)Project Ending2–4 → 664–12
T22 Product consolidation, packaging and qualification⧗Project Ending2–4 → 65–64–10
T24 Dust-tolerant long-life mechanisms and seals⧗Project Ending2–5 → 65–62–9
T25 Target-local and SEL1 cargo-node navigation and control⧗Project Ending2–4 → 64–64–9
T02 MW-scale deployable solar arrays (tug; site per Gemini and GPT)⧗Project Ending2–4 → 654–10
T07 Partial-gravity melting and slag/metal separation in a rotating moduleArchitecture Change2–3 → 66–75–12
T17 H2 reduction of the reducible feed fraction with H2 recycleArchitecture Change2–4 → 66–74–10
T06 No-melt carbonyl refining with CO recycle (Gemini: carbonyl or H2 reduction combined)Architecture Change2–3 → 664–10
T09 High-voltage power tethers and site distribution on regolith⧗Architecture Change2–4 → 65–63–7
T12 Autonomous handling, docking and transfer of 150-300 t payloads⧗Architecture Change2–4 → 65–63–12
T13 Asteroid water extraction pilotArchitecture Change2–4 → 65–63–10
T23 Native-metal production/consolidation in rotating modules (GPT route)Architecture Change2–3 → 664–12
T20 Distributed energy storage (GPT: and microgrid power management)⧗Architecture Change3–5 → 64–52–6
T26 Deep-space communications and resilient command service⧗Architecture Change3 → 641–5
7.

Validation Roadmap

The development paths of the 17 project-ending technologies, grouped by the TRL each step reaches. Steps and costs are the panel's, attributed in each technology's path.

Foundation: to TRL 4 (laboratory)

before the 0A mid-term review · 76 steps

  • T04 Requirement closure: mass-balance rate, reaction force/torque, anchor capacity vs cohesion, power reconciliation
  • T04 Material envelope and simulant calibration: returned-sample geotechnics; vacuum shear, penetration, abrasion and pull-out tests; target-class simulant (Claude: metal-bearing OC; Gemini: CI/CM; unresolved)
  • T04 Calibrated DEM with cohesion, clasts and electrostatics. Claude requires blind predictions before C4; Gemini re-runs torque cancellation with TAG parameters
  • T04 Reduced-gravity critical-function tests (parabolic/drop tower): cut, capture, anchor pull-out, asymmetric engagement
  • T04 Integrated anchor-plus-excavator breadboard: Claude ≥1/3 scale in thermal vacuum with charged simulant; GPT ~full size at 1 g, 0.5–5 t/h, six-axis loads, fault recovery
  • T08 Requirement definition and escape-budget allocation. Define "escaped" and the containment boundary; set size coverage; allocate the budget across nominal leakage, chronic pile loss and abnormal events; set uncertainty and confidence-bound reporting.
  • T08 Modelling. Ejecta, tailings and heliocentric-stream modelling validated against SCI, DART and Bennu (Claude). Coupled DEM-electrostatic modelling of excavation and transfer (Gemini). Escape and receiver-contamination models validated blind against lab injections (GPT).
  • T08 Vacuum seal and interface leakage tests with charged simulant, including calibrated-release sensor tests and receiver coupons (GPT combines these).
  • T08 Microgravity release tests (parabolic flight, drop tower, suborbital): grain velocity distributions from bucket strikes, gate closure and jam clearing.
  • T16 Load envelope, environment definition and heritage audit. rq-0-26 DEM six-axis spectra; tether, plant and tailings loads; per-variant relevant-environment definition from Bennu, Ryugu, Itokawa, Eros and Dimorphos data; recovery of original microspine and ARM test data.
  • T16 Instrumented anchor breadboards: pull-out, lateral, cyclic and set/release tests against prediction. Microspines and drilled bolts on boulder simulants and Fe-Ni; grouted or sintered anchors in cohesion-scaled media; subscale girdle; 1–20 kN, 10⁶ cycles, vacuum thermal cycling 150–400 K.
  • T16 Test-calibrated coupled granular, structural and control models (boulder motion, terrain evolution, creep)
  • T19 Relevant-environment and feed definition: PSD, cohesion, charge, abrasivity, liberation, Bond-number envelope, availability and buffer sizing
  • T19 Calibrated DEM / contact / charge / wear models, with scaling law to full rate
  • T19 Integrated ground vacuum breadboard, orientation-independent, with injected upsets and conditional milling
  • T11 Define recoverable grade and sampling requirements (depth, locations, representative mass, uncertainty; separate native metal from oxides, sulfides and water)
  • T11 Blind remote-vs-returned-sample grade test (Itokawa, Ryugu, Bennu). Decides whether sampling is needed and informs the §3.4 risk dispute
  • T11 Blind assay and recoverability tests on meteorite analogues and mixtures, with recovery mass balance
  • T11 Sampler breadboard (with assay interface) in vacuum, against known-grade or heterogeneous simulants. Claude: 2–3 competing routes, 0.1 Pa–10 kPa cohesion. GPT: 0.1–1 m beds with hard clasts
  • T18 Step 1. Gate specification and sampling statistics (analysis)
  • T18 Step 2. Laboratory breadboards → TRL 4
  • T18 Step 3. Subsurface access and relevant-environment components → TRL 4–5 or 5
  • T01 P1. Evidence audit and requirements baseline
  • T01 P2. Facility capability
  • T01 P3. Propellant-specific critical-function tests
  • T01 P4. Full-power module breadboard with PPU
  • T03 Route heat balance, heat partition and NEA relevant-environment definition; heritage audit
  • T03 Dust, coating and charging tests with NEA simulants, including EDS
  • T03 Critical-function and panel breadboards in vacuum: leak and puncture isolation; condensing heat exchanger for route
  • T05 Feed characterisation and evidence audit: Itokawa grains via JAXA AO (Claude); minimally weathered H/L/LL falls; CT, SEM/EBSD; measured liberation curves
  • T05 Representative feed: crushed W0–W1 ordinary chondrites (Claude); engineered metal-in-matrix simulant (Claude, GPT); M-type simulant (Gemini)
  • T05 1 g integrated breadboard (comminution + feed + LIMS). Predictions registered in advance; closed mass balance; grade, recovery, specific energy, fines, wear.
  • T05 Downstream-route qualification with the qualified concentrate (carbonyl, H₂ if applicable, or rotating smelting)
  • T10 Requirements, fault catalogue, relevant-environment definition and evidence audit. Includes per-target conjunction duration, a measurable definition of "unattended" or "intervention", minimum throughput, debris limits, and retrieval of heritage and rq-0-26 reports.
  • T10 Analogue intervention-rate review (Mars conjunction operations, RAX/ASE, autonomous-mining vendors)
  • T10 Breadboard or simulation to reach TRL 4. Three variants are proposed:
  • T10 • Excavation reflex breadboard: force/torque sensing, seeded voids, boulders and transitions, DEM-predicted
  • T10 • Integrated hardware-in-the-loop breadboard with 6–20 emulated agents and a 90-day fault-injection run
  • T14 Close requirements (max inventory, transfer batch, transfer vs tank swap); propellant trade; define relevant environment and scaling requirements; correlate models
  • T14 Materials and component endurance (iodine-wetted valves/seals; argon valves/leakage)
  • T14 Iodine sublimation feed breadboard at full flow
  • T14 Liquid-iodine store and transfer breadboard
  • T15 Architecture trade and requirements/heritage audit. Covers surface, cabled and beamed options × voltage × storage, coupled to each metallurgy route's load profile. Defines delivered vs nameplate power, continuous vs production-window duty, and repair policy. Obtains primary test reports.
  • T15 NEA environment definition from Bennu/Ryugu data and scout payloads (dust counter, Langmuir probe, PV coupons, rotation measurements)
  • T15 Option down-select at 0A mid-term (Claude), informed by step 2. Resolves §3.1 and §3.2.
  • T15 If free-flyer retained: high area-to-mass station-keeping simulation validated against OSIRIS-REx/Hayabusa2 data
  • T15 If surface retained: anchoring and array-mount pull-out tests in rubble-pile simulant plus DEM
  • T15 kV trunk, connector and fault-protection breadboard at the actual proposed voltage, in a plasma chamber with charged abrasive regolith simulant, with insulation ageing
  • T15 Rad-hard kV SiC/GaN converter: single-event burnout characterisation and derating; modular DC-DC breadboard in TVAC
  • T15 Beaming ground test, only if beaming survives Gate A
  • T21 Evidence baseline and wear/failure database: terrestrial mining and comminution, Apollo dust, vacuum tribology, flight servicing, HV
  • T21 Route-by-route FMECA, service envelope (replaceable units, masses, extraction forces, fault classes), maintenance-demand and sparing model with 1.5–5 yr resupply latency, fed into the delivered-cost model
  • T21 Vacuum abrasion, wear and galling tests on teeth, liners, seals, bearings and fasteners, using CI/CM and metal-rich simulants, thermal cycling and long dwell
  • T21 Tether insulation abrasion and vacuum-arc tests (rq-0-60), fault location, splice versus segment-replace breadboard. GPT adds that electrical isolation and proof of a safe state must precede cable manipulation
  • T21 Dust-tolerant cartridge, connector and tool-change interface testing, thousands of robotic cycles in dusty thermal-vacuum
  • T21 Lab service and recovery breadboard: full-size interfaces, worn parts, jams, damaged cables, hardware-in-the-loop autonomy with fault injection. GPT asks for jam detect, retreat, retry and handoff coupling with rq-0-42
  • T21 *Smelter route only:* rotating-furnace refractory relining breadboard, 1 g then partial-g analogue
  • T22 Boundary decision: does acceptance and qualification sit in T22 or the D-02 gate?
  • T22 Phase 1 product specification, acceptance plan, and relevant-environment document (tug loads, D-03 dust allocation, iodine compatibility if D-05)
  • T22 Representative feed and route-specific lab proof
  • T22 Vacuum consolidation breadboards (press, briquette, sinter, NVD, cast), each compared against prior prediction
  • T22 Integrated terrestrial breadboard or thermal-vacuum line
  • T22 Packaging breadboard and environmental campaign (thermal cycling, charged abrasive dust, closure faults, ageing, tare trade)
  • T22 Autonomous lot-qualification suite (major elements, C/S/O/N, density, hardness) validated against laboratory reference assays
  • T24 Requirements and heritage audit. Recover the KSC/GRC test reports; define loads, speeds, leak limits, kV and connector duty, and mate cycles. This should precede any TRL upgrade.
  • T24 NEA relevant-environment specification: grain properties, metal fraction, charging, ejecta. Draws on Itokawa, Ryugu and Bennu sample data and on scout measurements.
  • T24 Metal-bearing NEA simulant and a dusty TVAC facility with charging and thermal cycling.
  • T25 Relevant-environment and requirements definition: node structure, SEL1 orbit family, peak and average traffic, stack mass/inertia/array modes, D-03 debris source term
  • T25 Heritage data mining and model correlation
  • T25 6-DOF multibody / contact simulation and Monte Carlo
  • T02 Relevant-environment and requirement closure: max distance, trajectories, proton/electron fluence, plume backflow, thrust/slew load spectra, dust deposition. Correlate heritage structural models with test data
  • T02 Cell, coverglass and blanket irradiation (interplanetary spectra) with UV and thermal exposure; combined-stress sequences
  • T02 Iodine/argon exposure of coverglass, interconnects, hinges and slip rings; charged NEA dust adhesion and abrasion
  • T02 High-voltage (300 V to 1+ kV, up to site 1–3 kV) plasma interaction, arcing and fault isolation
  • T02 Multi-wing dynamics, control and thrust coupling model validated on ROSA/iROSA flight data
  • T02 Site-specific dust and anchoring/station-keeping demo (coupon or kW scout payload, or representative installation)

Relevant environment: TRL 5

pathfinder and ground campaigns · 45 steps

  • T04 Accelerated wear/endurance in vacuum with abrasive charged simulant (Claude ≥1.5× five-year contact passes; GPT 2,000–11,000 equivalent hours, including tether loads and seals)
  • T04 LEO free-flyer / ISS-external contained excavation; bed boundaries must not give artificial confinement or anchor support (GPT)
  • T04 Scout-borne geotechnical package at target NEA (penetrometer, pull-out, cut-force probe). Per Claude, this closes the TRL 4 environment-definition criterion
  • T08 Escape-verification breadboard: optical tracking, impact detectors and witness plates; low-speed calibration rig; detection-limit analysis against 1 t/yr and 10 kg/yr.
  • T08 Tailings stabilisation and endurance: bagging, compaction and sintering; fines liberation rate; fault injection; closure and reopening.
  • T08 Array and radiator contamination under charged ballistic flux; separate deposition limits for photovoltaics, optics and radiators.
  • T16 Tailings retention breadboard: bagging, compaction, sinter-blocking; loss fraction measured against ≥99.99%
  • T16 Reduced-gravity transients plus long-duration creep and life tests (drop tower, parabolic, suborbital, ISS/free-flyer loaded STRATA-type; accelerated life to 3,900–11,000 h and 5-yr equivalence)
  • T16 Integrated restraint and tethered-mobility prototype (excavator-interface simulator, plant fixtures, powered tether, tailings interfaces, relocation and re-anchoring, fault recovery; realistic confinement)
  • T19 Reduced-gravity / relevant-environment component campaign
  • T19 Wear and life testing
  • T19 Long-duration microgravity flight pilot (0A pathfinder or LEO free-flyer), with upset injection and mass-balance closure
  • T11 Relevant-environment tests: reduced-gravity contact and anchoring, TVAC, abrasion and charging, reuse cycles; route downselect (Claude)
  • T18 Step 4. Define the subsurface environment
  • T01 P5. Wear and relevant-environment testing
  • T01 P6. Life and throughput closure
  • T03 Rotary fluid-joint life test (rotating route only)
  • T03 Relevant-environment module
  • T03 Plant subsystem at TRL 6
  • T05 DEM model with cohesion, magnetic and triboelectric forces, calibrated on C3/C5 and extrapolated to full throughput
  • T05 Short reduced-gravity tests: parabolic flight; evacuated drop tower
  • T05 Thermal-vacuum, abrasion and endurance testing
  • T05 Long-duration microgravity vacuum separation experiment (ISS external or free-flyer)
  • T10 • Integrated software-in-the-loop simulation of fleet and plant
  • T10 Plant FDIR breadboards per route in thermal-vacuum with fault injection. Claude would fund no-melt and native-metal first and gate the furnace on furnace TRL 4.
  • T10 Relevant-environment campaign to reach TRL 5. Three variants are proposed:
  • T10 • Reduced-gravity contact and anchoring campaign. Claude notes it is for DEM validation only, because these facilities cannot reach 10⁻⁶–10⁻⁴ g for long durations.
  • T10 • Vacuum, thermal, abrasive and charging tests, gravity offload, 0.05–0.15 g rotating rigs and radiation tests
  • T14 Argon 87 K zero-boil-off tank + cryocooler + feed, thermal vacuum
  • T14 HP argon COPV module and regulated feed qualification
  • T14 Integrated laboratory breadboard of the selected route
  • T14 Microgravity transfer tests and model anchoring
  • T15 Blanket campaign: dust, UV, thermal cycling, 0.9–1.3 AU irradiation; dust-shield and coverglass variants. Replaces the RQ-0-25 L4/L5 framing.
  • T15 Relevant-environment subsystem / array-module development, shared with tugs per Claude: 1 g-offload deployment, TVAC, hardware-in-the-loop dynamic deployment and fault tests, scaling requirements documented
  • T21 Relevant-environment component campaign: thermal-vacuum, charged simulant, 1–3 kV, contaminated seals, route-specific modules, radiation
  • T21 Full-mass microgravity handling and recovery testbed: gravity offload or air bearing with a 2–3.5 t mock robot, anchoring, module exchange, entrapped-robot extraction, parabolic flights, DEM validated on flight contact data
  • T22 Reduced-gravity powder feed, die fill, canister fill and mould fill (parabolic flight, drop tower; rotating ground tests as a supplement), with DEM validation
  • T22 Casting branch only: partial-g casting trials
  • T24 Component screening and breadboards: bearings, seals, lubricants, competing seal concepts, kV slip-ring arcing tests.
  • T24 Wear, leak and acceleration models correlated to tests.
  • T24 Relevant-environment and full-scale component endurance to 1.5× life (Claude), or combined-environment tests (GPT).
  • T25 HIL / air-bearing / robotic contact and GNC breadboard
  • T25 Relevant-environment component and scaling campaign: thermal-vacuum, radiation, dust/illumination, flexible-mode and capture-impedance tests
  • T02 Wing or repeat-unit ground test (50–250 kW): deployment, gravity-offload modal, TVAC, electrical
  • T02 MW integrated ground validation: 1–2.5 MW tug electrical architecture, 2.5–8 MW site aggregation, hardware-in-the-loop controls, full-scale critical spans

Demonstration: TRL 6 and beyond

required before KDP-0B · 42 steps

  • T04 0A NEA pathfinder: anchored, tethered excavation with measured force/torque spectra, throughput, anchor recovery and escaped mass, judged against predictions (GPT)
  • T08 Long-duration seal and active-cleaning endurance in a vacuum plasma chamber.
  • T08 Integrated full-feed ground pilot, route-specific, with abnormal-event testing. Claude notes it needs a dedicated "dirty" chamber.
  • T08 NEA pathfinder in-situ containment experiment with calibrated escape measurement and witness surfaces.
  • T16 In-situ geotechnical payload on 0A scouts (penetrometer, shear vane, pull-out, boulder grip)
  • T16 NEA pathfinder hold-down demonstration. Representative anchor geometry; 10–30% of design load, including residual torque; 6–12 months; tether interaction; plant-mount and tailings-containment sub-demos; correlated with the ground life test.
  • T19 Production-representative qualification at module operating flow, with endurance
  • T19 Rotating-route flight loop, including static-to-rotating interface
  • T11 Trajectory and propellant closure on real candidates (1-, 2- and 3-target cases; Claude adds xenon and iodine cases; with rq-0-52)
  • T11 Engineering model: Claude, sampler integrated with touchdown GNC, hardware-in-loop; Gemini, full 200–600 kg scout EM
  • T11 (Conditional) kW-class iodine thruster life test, only if iodine is adopted
  • T11 Flight. Claude: first scout samples at depth on targets 1 and 2. GPT: one-scout pathfinder at one NEA, multiple sites, assay or returned-sample cross-check; second candidate needed separately for rq-0-50. Gemini: flight qualification of 0A units
  • T18 Step 5. Integrated system demonstration → TRL 6
  • T18 Step 6. Flight target-gate campaign
  • T18 Fallback branch (D7, unresolved)
  • T01 P7. Cluster demonstration
  • T01 P8. Post-KDP-0B life extension
  • T01 P9. In-space module demo (optional)
  • T03 Flight element
  • T03 Tug thermal subsystem
  • T05 0A pathfinder at target NEA: full closed train measuring ratio, grade, recovery, fines escape and autonomy
  • T10 • Vacuum-chamber mining breadboard run 30+ days unattended under light-time delay
  • T10 Integrated 90-day rehearsal with light-time delay, full conjunction blackout and blind fault injection
  • T10 Scout-borne demonstrations: planner through a real conjunction, touch-and-go and anchoring, regolith-mechanics measurement
  • T10 NEA pathfinder, ≥90 days of autonomous operation, including a blackout of full target length
  • T14 Relevant-environment module campaign / thermal-vacuum prototype
  • T14 Full-flow feed endurance coupled to thruster life test
  • T14 Orbital demonstrator: storage, feed and 1–5 t transfer or tank swap
  • T14 Bulk ground prototype and life closure
  • T15 Pathfinder flight power experiment: array, trunk and robot-tether load, ≥1 yr operation. Gemini allows LEO as an alternative location.
  • T15 Integrated 0.25–1 MW representative module and distribution zone at full rated voltage, current and fault energy, with a test-calibrated lifetime and scaling case to 8 MW
  • T15 Explicit KDP-0B ruling on whether step 9 alone, or steps 9 and 10, constitute TRL 6 for 2.5–8 MW (§3.4). Claude asks that this be decided explicitly rather than assumed.
  • T21 Long-duration integrated and life campaign: Claude's months-long autonomous dusty-thermal-vacuum run with latency and injected faults; GPT's parallel life rigs, validated accelerated ageing, stockout analysis
  • T21 Flight demonstration: anchoring, module or cartridge exchange after regolith exposure, tether deploy and recover, failure recovery, correlated with ground data
  • T22 Space demonstration: consolidation, packaging and qualification
  • T22 Scaling and endurance closure on a representative production module
  • T24 Milligravity dust transport: parabolic and drop-tower tests, plus a scout-hosted exposure package (Claude) or reduced-gravity-anchored models (GPT).
  • T24 Integrated subsystem demonstration. The models propose different forms.
  • T25 0A flight experiments, 200–600 kg: NEA low-thrust proximity and debris avoidance; SEL1 release/recapture or scout-to-scout rendezvous
  • T25 ~10–30 t integrated space prototype with large flexible array, repeated captures and injected-fault aborts, plus full-scale correlation
  • T02 Relevant-environment flight demonstration with EP at thrust and selected propellant
  • T02 Space-grade cell supply-chain analysis versus 30–180 MW fleet need
8.

Conclusions and What Would Change Them

Assessment

Phase 0 is feasible as a research and pathfinder programme. Whether asteroid production (0B) is feasible is not yet known, and the plan is built so that this does not need to be known now. 17 project-ending technologies sit at TRL 2–5 and must reach TRL 6 before KDP-0B. 4 discriminating gates must also pass for the same configuration: a sampled target, signed demand, delivered cost against Earth supply, and a licence.

Next steps

  1. Answer the evidence questions behind the open gate rulings:
    • rq-0-76 How do agencies set composite TRLs, scale limits for TRL 6 and the readiness of flown experiments? (high)
    • rq-0-77 Does each split technology have a credible, costed fallback that keeps 0B production viable? (critical)
    • rq-0-78 How far have space and process technologies been extrapolated from test to flight or plant, and where did scale-up fail? (high)
    • rq-0-79 Can ground facilities plus a cluster model take MW-class EP (T01) to TRL 6, and what would a flight subset cost? (critical)
    • rq-0-80 What sampling and assay evidence bounds a target's bulk grade well enough for the target gate and KDP-0B? (critical)
    • rq-0-81 What counts as bankable demand for Phase 0 output, and what nameplate capacity does it justify? (critical)
    • rq-0-82 Which cost statistic should the economics gate use, and how do public programmes authorise an above-market capability premium? (critical)
    • rq-0-83 What do programme sunsets, option preservation and licence reapplication cost and take in practice? (high)
  2. Rule on the 11 gate questions as their evidence reports, then fix the gate thresholds.
  3. Sign off the proposed decisions (D-03, D-04, D-05), now used as interim positions.
  4. Rebuild the BOM and cost from the agreed architecture, keeping each model's figures.

What would change the assessment

D-01 rests on these assumptions. Each line names the evidence that would falsify it.

AssumptionFalsified by
A1: the swarm thesis needs in-space material by Phase 2Phase 2 mass demand fits within plausible launch capacity and price
A2: delivered launch price stays above ~$1,000/kg to LEO through Phase 1Sustained quotes below that (rq-0-57)
A3: an accessible NEA has ≥5% recoverable Fe-Ni0A rendezvous and sampling below that (rq-0-50)
A4: 0A ($3.5–16B) is fundableNo funding path; then O0 by default
A5: beneficiation ≥3:1 in microgravityClaude's falsifier: below 3:1 (rq-0-51)

Sources: reconciliation/phase-0/decisions.md, the open-question register, and the TRL re-baseline (2026-10-17). See also rq-0-62 (Technology readiness re-baseline for the revised Phase 0 architecture).

Project Dyson — A volunteer-led nonprofit. All plans and research are publicly available.