Investigating
Integrated schedule for Phase 0A, the gates and the 0B ramp
Analysis High
schedulegatesplanning
Background
No panel model produced an integrated schedule; only fragments (Claude: 3–6 yr delay; GPT: deliveries ~3 yr after 0B authorisation). Several critiques cite schedule as a decision criterion, and CI-18 found the existing gates scheduled before their technologies are ready.
Raised by the Phase 0 re-assessment (round 2, 2026-10-12): reconciliation/phase-0/round-2/reconciliation/phase.md and reconciliation/phase-0/decisions.md.
Why This Matters
Gates must be timed to technology readiness, and D-01 accepts a delay whose size is unknown.
How this gets answered
- Analysis — Critical-path schedule from the TRL re-baseline (rq-0-62), test campaigns and launch windows, with cost of delay per gate.
Research Directions
- Earliest KDP-0B date by technology.
- Cost of delay per month.
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Organizational Infrastructure
- Question ID
- rq-0-63
- Created
- 2026-10-12
- Related BOM Items
- bom-0-7bom-0-3bom-0-4
Related Questions
Governance structure for multi-century, volunteer-driven global coordination
critical - open
Post-scarcity economic valuation frameworks for self-replicating systems
medium - open
What should the TRL rating of deep-space communications and command (T26) assess?
high - answered
Which risk class should apply to the eight technologies the panel split on (T02, T10, T14, T15, T22, T24, T25, T26)?
high - investigating
Must T11, T18, T09, T12 and T20 be at TRL 6 at KDP-0B?
high - investigating