Which risk class should apply to the eight technologies the panel split on (T02, T10, T14, T15, T22, T24, T25, T26)?
Background
The Phase 0 TRL re-baseline (work package WP-A, reconciliation/phase-0/trl/) has produced a gate proposal under owner decision D-02: three programme decisions (KDP-0A, a 0A mid-term review, KDP-0B), four discriminating gates TRL cannot express (target, demand, economics, licence) and pre-committed failure outcomes. The panel (Claude Opus 5.5, Gemini 3.1 Pro, GPT-6.1 Sol) agreed on that structure, on TRL 6 in a relevant environment with no waiver for project-ending technologies at KDP-0B, and on the fallback "0A only, Earth supply". It left eleven choices for the owner. This question is one of them.
D-01 (accepted): fund 0A; hold 0B as a gated real option sized at the gate by signed Phase 1 demand; call Phase 0 a capability programme, not a cost saving. D-02 (accepted): stringency follows reversibility; one-way gates (KDP-0B) need TRL 6 in a relevant environment for project-ending technologies with no waivers; two-way internal 0A milestones need TRL 4–5. Gemini's gate response was brief, so several positions below are Claude against GPT; where Gemini is silent that is not agreement.
Sources: reconciliation/phase-0/trl/round-1/gates/synthesis/gates.md, gates-proposal.yaml, trl-baseline.yaml, reconciliation/phase-0/decisions.md.
What the panel said
| Technology | Claude | Gemini | GPT | Panel headline |
|---|---|---|---|---|
| T02 MW-scale deployable solar arrays (tug; site per Gemini and G | TRL 2–4, AD² 5, architecture-change | TRL 3–4, AD² 5, architecture-change | TRL 2–3, AD² 5, project-ending | TRL 2–4, project-ending |
| T10 Long-duration autonomy for mining, processing and proximity | TRL 2–3, AD² 6, architecture-change | TRL 3–4, AD² 6, project-ending | TRL 3–4, AD² 6, project-ending | TRL 2–4, project-ending |
| T14 Propellant storage and feed at hundreds of tonnes per tug | TRL 2–4, AD² 5, architecture-change | TRL 2–3, AD² 6, architecture-change | TRL 2–3, AD² 6, project-ending | TRL 2–4, project-ending |
| T15 Site power generation and transfer | TRL 2–3, AD² 6, architecture-change | TRL 2–3, AD² 6, project-ending | TRL 2–3, AD² 5, project-ending | TRL 2–3, project-ending |
| T22 Product consolidation, packaging and qualification | TRL 2–4, AD² 5, project-ending | TRL 2–3, AD² 6, architecture-change | TRL 2–2, AD² 6, project-ending | TRL 2–4, project-ending |
| T24 Dust-tolerant long-life mechanisms and seals | TRL 2–4, AD² 6, architecture-change | TRL 4–5, AD² 5, project-ending | TRL 3–4, AD² 6, project-ending | TRL 2–5, project-ending |
| T25 Target-local and SEL1 cargo-node navigation and control | TRL 2–3, AD² 5, architecture-change | TRL 3–4, AD² 4, project-ending | TRL 2–3, AD² 6, architecture-change | TRL 2–4, project-ending |
| T26 Deep-space communications and resilient command service | TRL 5–7, AD² 3, cost-increase | TRL 6–7, AD² 3, cost-increase | TRL 3–4, AD² 4, architecture-change | TRL 3–3, architecture-change (owner ruling) |
Claude's list of split classes needing a ruling: T02, T10, T14, T15, T22, T24, T25, T26. Claude holds these at TRL 6, no waiver, until they are ruled on. T26 already carries an owner ruling from rq-0-64 (architecture-change, possibly project-ending).
Project-ending classification for KDP-0B
Agreed core (all three models): T01, T02, T03, T04, T05, T08, T10, T14, T15, T16, T19, T21, T22, T24.
Disputed members:
| Technology | Claude | Gemini | GPT |
|---|---|---|---|
| T25 | Project-ending (split; ruling due at KDP-0A) | Project-ending | TRL 6 as "selected reference implementation," grouped with T09, T12, T20 |
| T26 | Claude's view: project-ending for integrated fleet command. Owner ruling is architecture-change, "possibly project-ending." Open in rq-0-64. | Not listed | TRL 6 integrated service at KDP-0B |
| T18 | 0A flight technology (TRL 6 at scout PDR) | Project-ending | TRL 6 technology maturity before KDP-0B |
| T11 | 0A flight technology | In prose list; absent from YAML | TRL 6 technology maturity before KDP-0B |
| T09, T12, T20 | Architecture-change: TRL ≥ 5, waiverable, with a funded path to 6 | Not listed | TRL 6 for selected implementations; substitutions reassessed |
Split classes needing an owner ruling (Claude's list): T02, T10, T14, T15, T22, T24, T25, T26. Claude holds these at TRL 6, no waiver, until they are ruled on.
Why This Matters
The class decides whether a technology must be at TRL 6 with no waiver at KDP-0B (project-ending) or may pass at a lower level with a funded path (architecture-change, schedule-delay, cost-increase). Over-classing lengthens 0A; under-classing lets 0B commit on an unproven function.
Key Considerations
- Rule per technology, or a rule that generates the classes (e.g. 'project-ending if no credible fallback keeps 0B production').
- Whether the fallbacks the models named are credible and costed.
- How the ruling interacts with rq-0-64 for T26.
Research Directions
- Decide the ruling, with the criteria stated first and the null option (leave the panel's split as is) assessed.
- State the gate criterion or rule text that follows from it.
- Name the evidence that would change the ruling.
Status (2026-10-20)
No part of this question converged in both syntheses, so nothing is ruled yet. The deliberation could not settle the rest: the positions turn on evidence nobody supplied, and on practice the panel was not given. The open choices (decision sheet reconciliation/phase-0/trl/gate-rulings-sheet.md) are routed to evidence questions: rq-0-76, rq-0-77. This question stays open until they report; then the owner rules, or the panel deliberates again with that evidence.
Multi-Model Discussion
ConcludedRound Winners
Discussion Conclusion
Synthesized by GPT-6.1 SolSummary
Claude Opus 5.5 and GPT-6.1 Sol converged on an evidence-conditioned rule: classify a function as project-ending unless an independently reviewed fallback preserves viable, authorised 0B production. Gemini 3.1 Pro also favoured classification by fallback viability, but considered several alternatives sufficiently credible to justify architecture-change immediately. Thus, the panel shared a governing principle but did not converge on all eight classifications or on the evidence needed before lowering a class.
GPT recommended project-ending for T02, T10, T14, T15, T22, T24 and T25, retaining T26 as architecture-change subject to a KDP-0A closure test. Claude recommended project-ending for T02, safety-critical T10 and T15/T22, while proposing conditional or provisional architecture-change treatment for productivity T10, T14, T24 and T25. Gemini recommended project-ending for T10, T14, T24 and T25, and architecture-change for T02, T15, T22 and T26. All three retained T26’s existing architecture-change classification; GPT additionally proposed automatic elevation if its closure test failed.
The votes exposed the main unresolved issue: Claude and GPT both identified a contradiction between Claude’s project-ending default and its immediate lowering of classes before fallback dossiers were accepted. Claude and GPT also rejected Gemini’s lower classifications as resting on unevidenced fallback assumptions. GPT’s response received approval from all three models, but those approvals did not establish an explicit revised classification agreement from the other two respondents.
Decision record
Claude Opus 5.5: function-level classification with conditional lower classes
Y-statement: In the context of D-01/D-02 and a one-way KDP-0B commitment, facing disagreements Claude attributed mainly to inconsistent scope and definitions, Claude chose a function-level fallback rule, to protect 0B while avoiding unnecessary qualification, accepting additional 0A work and dependence on independent dossier review.
- Warrant: Claude argued that consequences and fallback viability—not model votes—should determine class.
- Proposed classifications:
- Project-ending: T02; T10a, safety-critical autonomy; T15; T22.
- Architecture-change, conditional or provisional: T10b, productivity autonomy; T14; T24; T25.
- T26: retain architecture-change under rq-0-64; leave possible elevation to that decision.
- Qualifier: Claude’s written rule made project-ending the default until an accepted fallback dossier existed.
- Accepted downside: Claude accepted potentially longer TRL 6 holds and the risk of optimistic fallback costing.
- Recorded inconsistency: Claude’s self-review and GPT’s vote both said the conditional lower classifications contradicted that default.
Gemini 3.1 Pro: split according to asserted fallback viability
Y-statement: In the context of the KDP-0B gate, facing disputed classifications, Gemini chose to distinguish core operating technologies from technologies with alternative implementations, to balance 0A schedule with commitment protection, accepting that the alternatives might degrade Phase 1 economics.
- Warrant: Gemini argued that project-ending should be reserved for technologies without viable functional fallbacks.
- Proposed classifications:
- Project-ending: T10, T14, T24, T25.
- Architecture-change: T02, T15, T22, T26.
- Qualifier: Gemini assumed smaller arrays, localised power, Earth-based packaging and existing communications services would preserve acceptable economics.
- Accepted downside: Gemini accepted economic degradation from those alternatives.
- Recorded challenge: Claude and GPT rejected the decisive fallback claims as insufficiently evidenced.
GPT-6.1 Sol: conservative current classes with an evidence-based exit
Y-statement: In the context of funded 0A and optional 0B production, facing unresolved classifications and unevidenced fallbacks, GPT chose seven project-ending classifications and a time-bounded architecture-change ruling for T26, to protect irreversible investment while permitting demonstrated substitution, accepting additional qualification effort and possible delay or rejection of 0B.
- Warrant: GPT argued that indispensable production functions require demonstrated capability or an evidenced substitute before commitment.
- Proposed classifications:
- Project-ending: T02, T10, T14, T15, T22, T24, T25.
- T26: architecture-change under rq-0-64, with a proposed KDP-0A test; failure would elevate the affected capability to project-ending.
- Qualifier: GPT allowed reclassification following owner acceptance of an independently reviewed, architecture-specific fallback package.
- Accepted downside: GPT accepted additional 0A analysis, testing and possible delay.
- Voting outcome: Claude, Gemini and GPT approved this response; neither Claude nor Gemini supplied a revised classification table explicitly adopting it.
Decision-quality audit
Round 1
| Response | Weakest links named in votes | Missing or unsupported Composite Scaffold elements |
|---|---|---|
| Claude | Claude: reasoning; GPT: commitment; Gemini: none | Claude and GPT identified a mismatch between the generating rule and the operative classifications in the decision step. Claude also identified minor assessment-matrix arithmetic errors. Gemini approved the overall decision chain. |
| Gemini | Claude and GPT: information; Gemini: information | Claude challenged the qualitative weights and matrix, thin certainty claims, and unsupported fallback evidence. GPT challenged the architecture-specific evidence and calibrated confidence, especially for T26. Gemini’s self-review identified the absence of a structured ACH analysis. |
| GPT | Claude: alternatives; GPT: information; Gemini: none | Claude said the all-project-ending and evidence-conditioned options differed mainly in the reclassification path, and noted minor arithmetic errors. GPT acknowledged that the record contained no supporting fallback studies or test reports. All three nevertheless approved the response. |
Trade-off points, rather than facts to settle
- Burden of proof: Claude and GPT explicitly favoured a project-ending default; both framed the balance between extra 0A work and irreversible 0B exposure as an owner value judgment.
- Acceptable degraded production: Claude and GPT said the owner must define how much throughput, schedule or cost degradation still counts as a successful 0B fallback.
- Meaning of “project-ending”: Claude recommended a definition tied to viable 0B production; GPT explicitly distinguished ending the proposed 0B commitment from ending the funded 0A programme.
- Schedule versus assurance: Gemini explicitly prioritised a balance between 0A velocity and KDP-0B confidence.
- Not merely a trade-off: Claude and GPT treated fallback performance, maturity, cost and independence as evidence questions—not matters that an owner preference alone could settle.
Key Points
- Shared principle, disputed application: All three responses used fallback viability to distinguish classes. Claude and GPT required stronger evidence before lowering them than Gemini supplied.
- The source labels need care: GPT warned that the background’s “agreed core” was not evidence of unanimous original classifications. Claude likewise identified scope and definition inconsistencies, including its own T25 entries.
- T10 may need functional separation: Claude proposed separating safety-critical autonomy from productivity autonomy. GPT supported splitting broad technology IDs where necessary, but retained T10 as project-ending in its current table.
- TRL and consequence are different: Claude and GPT argued that current maturity estimates or familiar components do not establish that a function is replaceable.
- The economics gate is not sufficient by itself: Claude and GPT rejected using economics modelling to compensate for missing technical evidence about a fallback.
- T26 has a narrower agreement: All three retained architecture-change. Only GPT proposed automatic elevation at KDP-0A; Claude explicitly kept possible elevation within rq-0-64.
- Earth supply has two different roles in the responses: GPT treated “0A only, Earth supply” as a programme exit, not continued 0B production. Gemini proposed Earth-based packaging as a T22 fallback, which Claude and GPT considered insufficiently demonstrated.
Unresolved Questions
- Which classifications operate before dossiers are accepted? Claude’s rule implies project-ending holds, but its table grants several lower classes; Claude and GPT both flagged this contradiction.
- What constitutes an admissible fallback? Claude proposed explicit maturity, costing, economics, independence and schedule conditions. GPT proposed an independently reviewed qualification and transition package. Gemini did not establish comparable evidence thresholds.
- What degraded 0B remains authorised? Claude and GPT requested owner-defined production, cost and schedule boundaries.
- Which technology scopes should be controlled? Claude identified tug versus site power, safety versus productivity autonomy, and communications links versus integrated command service as important distinctions.
- How should T26 close? GPT proposed automatic elevation; Claude deferred that question to rq-0-64; Gemini considered existing communications alternatives credible.
- Can the economics model discriminate fallback branches? Claude said failure of that capability would undermine its proposed rule and favour conservative holds.
- What evidence exists beyond this record? GPT distinguished “not demonstrated in the supplied record” from “no fallback exists.”
Recommended Actions
The following actions reflect proposals made by the models, rather than a new classification ruling:
- Obtain an explicit owner decision on current classes. Claude and GPT’s reviews require resolving the contradiction between provisional architecture-change labels and a project-ending-until-evidenced rule.
- Record the generating rule alongside the classification table. Claude and GPT proposed independently reviewed fallback evidence; the owner should explicitly accept or modify the required thresholds.
- Define acceptable fallback outcomes at KDP-0A. Claude and GPT requested controlled limits for production, economics, safety, licence, schedule and cost.
- Commission bounded fallback packages. Claude proposed dossiers for T02, productivity T10, T14, T24 and T25; GPT proposed function-specific qualification and fallback packages across the disputed technologies.
- Control scopes before revising the baseline. Claude proposed splitting T10 and separating tug-array scope from site-power scope; GPT supported function-level decomposition where necessary.
- Close T26 through rq-0-64. Consider GPT’s proposed KDP-0A substitution/disconnection test explicitly, without presenting its automatic-elevation mechanism as already agreed.
- Preserve the independent gates and programme exit. GPT proposed retaining target, demand, economics and licence gates independently, with “0A only, Earth supply” if KDP-0B fails.
questionId: "rq-0-65"
topics:
- id: current-risk-classes
topic: Operative classifications for the seven technologies other than T26
positions:
- statement: "Classify T02, T10, T14, T15, T22, T24 and T25 as project-ending until an evidenced alternative warrants reclassification."
models: ["GPT-6.1 Sol"]
evidence: "Indispensable production functions and no qualifying fallback packages demonstrated in the supplied record."
- statement: "Keep T02, safety-critical T10, T15 and T22 project-ending; allow conditional or provisional architecture-change for productivity T10, T14, T24 and T25."
models: ["Claude Opus 5.5"]
evidence: "Proposed supervised operations, alternative propellants, replaceable mechanisms and cooperative navigation fallbacks; Claude and GPT subsequently flagged inconsistency with Claude's dossier-first rule."
- statement: "Classify T10, T14, T24 and T25 as project-ending, and T02, T15 and T22 as architecture-change."
models: ["Gemini 3.1 Pro"]
evidence: "Asserted fallback viability through smaller arrays, localised power and Earth-based packaging; Claude and GPT challenged the supporting evidence."
resolution_status: open
priority: critical
- id: fallback-admissibility
topic: Evidence required before lowering a risk class
positions:
- statement: "Require an accepted, independently reviewed fallback dossier before lowering a project-ending class."
models: ["Claude Opus 5.5", "GPT-6.1 Sol"]
evidence: "Both proposed architecture-specific performance, cost, schedule and dependency checks; Claude additionally specified maturity and costing thresholds."
- statement: "Known alternative implementations justify architecture-change, subject to economic viability."
models: ["Gemini 3.1 Pro"]
evidence: "Gemini's classification split relied on asserted alternatives and assumed acceptable Phase 1 economics."
resolution_status: partially-resolved
priority: critical
- id: t26-closure
topic: T26 architecture-change ruling and possible elevation
positions:
- statement: "Retain architecture-change and leave possible project-ending elevation within rq-0-64."
models: ["Claude Opus 5.5"]
evidence: "Existing owner ruling and proposed application of the fallback test within that decision."
- statement: "Retain architecture-change because existing deep-space communications services provide alternatives."
models: ["Gemini 3.1 Pro"]
evidence: "DSN and commercial service alternatives; GPT challenged whether fleet-level capacity and resilience were demonstrated."
- statement: "Retain architecture-change provisionally, with automatic elevation if substitution or tolerable disconnection is not demonstrated at KDP-0A."
models: ["GPT-6.1 Sol"]
evidence: "Existing owner ruling, unresolved integrated-service maturity and absence of demonstrated fallback service capacity in the record."
resolution_status: partially-resolved
priority: high
- id: authorised-fallback-outcome
topic: Definition of viable continued 0B production
positions:
- statement: "Judge fallbacks against owner-approved production and economic boundaries; define acceptable degradation explicitly."
models: ["Claude Opus 5.5", "GPT-6.1 Sol"]
evidence: "Both identified acceptable reduced output, cost and schedule as owner trade-offs rather than settled technical facts."
- statement: "Accept less efficient alternatives if the economics remain viable."
models: ["Gemini 3.1 Pro"]
evidence: "Gemini explicitly accepted degraded Phase 1 economics as the downside of its architecture-change classifications."
resolution_status: open
priority: high
Key Points of Agreement
- Shared principle, disputed application:** All three responses used fallback viability to distinguish classes. Claude and GPT required stronger evidence before lowering them than Gemini supplied.
- The source labels need care:** GPT warned that the background’s “agreed core” was not evidence of unanimous original classifications. Claude likewise identified scope and definition inconsistencies, including its own T25 entries.
- T10 may need functional separation:** Claude proposed separating safety-critical autonomy from productivity autonomy. GPT supported splitting broad technology IDs where necessary, but retained T10 as project-ending in its current table.
- TRL and consequence are different:** Claude and GPT argued that current maturity estimates or familiar components do not establish that a function is replaceable.
- The economics gate is not sufficient by itself:** Claude and GPT rejected using economics modelling to compensate for missing technical evidence about a fallback.
- T26 has a narrower agreement:** All three retained architecture-change. Only GPT proposed automatic elevation at KDP-0A; Claude explicitly kept possible elevation within rq-0-64.
- Earth supply has two different roles in the responses:** GPT treated “0A only, Earth supply” as a programme exit, not continued 0B production. Gemini proposed Earth-based packaging as a T22 fallback, which Claude and GPT considered insufficiently demonstrated.
Unresolved Questions
- Which classifications operate before dossiers are accepted?** Claude’s rule implies project-ending holds, but its table grants several lower classes; Claude and GPT both flagged this contradiction.
- What constitutes an admissible fallback?** Claude proposed explicit maturity, costing, economics, independence and schedule conditions. GPT proposed an independently reviewed qualification and transition package. Gemini did not establish comparable evidence thresholds.
- What degraded 0B remains authorised?** Claude and GPT requested owner-defined production, cost and schedule boundaries.
- Which technology scopes should be controlled?** Claude identified tug versus site power, safety versus productivity autonomy, and communications links versus integrated command service as important distinctions.
- How should T26 close?** GPT proposed automatic elevation; Claude deferred that question to rq-0-64; Gemini considered existing communications alternatives credible.
- Can the economics model discriminate fallback branches?** Claude said failure of that capability would undermine its proposed rule and favour conservative holds.
- What evidence exists beyond this record?** GPT distinguished “not demonstrated in the supplied record” from “no fallback exists.”
Recommended Actions
- Obtain an explicit owner decision on current classes.** Claude and GPT’s reviews require resolving the contradiction between provisional architecture-change labels and a project-ending-until-evidenced rule.
- Record the generating rule alongside the classification table.** Claude and GPT proposed independently reviewed fallback evidence; the owner should explicitly accept or modify the required thresholds.
- Define acceptable fallback outcomes at KDP-0A.** Claude and GPT requested controlled limits for production, economics, safety, licence, schedule and cost.
- Commission bounded fallback packages.** Claude proposed dossiers for T02, productivity T10, T14, T24 and T25; GPT proposed function-specific qualification and fallback packages across the disputed technologies.
- Control scopes before revising the baseline.** Claude proposed splitting T10 and separating tug-array scope from site-power scope; GPT supported function-level decomposition where necessary.
- Close T26 through rq-0-64.** Consider GPT’s proposed KDP-0A substitution/disconnection test explicitly, without presenting its automatic-elevation mechanism as already agreed.
- Preserve the independent gates and programme exit.** GPT proposed retaining target, demand, economics and licence gates independently, with “0A only, Earth supply” if KDP-0B fails.
- id: current-risk-classes
- statement: "Classify T02, T10, T14, T15, T22, T24 and T25 as project-ending until an evidenced alternative warrants reclassification."
- statement: "Keep T02, safety-critical T10, T15 and T22 project-ending; allow conditional or provisional architecture-change for productivity T10, T14, T24 and T25."
- statement: "Classify T10, T14, T24 and T25 as project-ending, and T02, T15 and T22 as architecture-change."
- id: fallback-admissibility
- statement: "Require an accepted, independently reviewed fallback dossier before lowering a project-ending class."
- statement: "Known alternative implementations justify architecture-change, subject to economic viability."
- id: t26-closure
- statement: "Retain architecture-change and leave possible project-ending elevation within rq-0-64."
- statement: "Retain architecture-change because existing deep-space communications services provide alternatives."
- statement: "Retain architecture-change provisionally, with automatic elevation if substitution or tolerable disconnection is not demonstrated at KDP-0A."
- id: authorised-fallback-outcome
- statement: "Judge fallbacks against owner-approved production and economic boundaries; define acceptable degradation explicitly."
- statement: "Accept less efficient alternatives if the economics remain viable."
Discussion Rounds
Responses
1. Frame & decision type
Recommendation: classify T02, T10, T14, T15, T22, T24 and T25 as project-ending for the selected 0B production architecture. Retain T26 as architecture-change under rq-0-64, but require a bounded closure test at KDP-0A; absent evidence that its loss is survivable, elevate it to project-ending.
The governing question is not “Could another engineering solution exist?” It is:
If this technology fails its qualification, is there an evidenced alternative that preserves an authorised 0B production capability before irreversible commitment?
“Project-ending” here means ending the proposed 0B production commitment, not cancelling the funded 0A capability programme. “0A only, Earth supply” is the programme’s safe exit under D-01—not a fallback that justifies admitting an immature 0B production architecture.
This is a property and executive decision: classification remains revisable during 0A, but determines assurance requirements at the one-way KDP-0B gate.
There is also a source-control issue. The supplied “agreed core” includes technologies whose individual panel classifications differ. I would treat that list as a proposed gate baseline, not evidence of unanimous agreement. The owner’s ruling must resolve this explicitly.
2. Criteria and weights
Non-compensable requirements
- Respect D-02: project-ending technologies require TRL 6 in a relevant environment at KDP-0B, without waiver.
- Preserve D-01: 0B remains a demand-sized real option; classification cannot create an obligation to proceed.
- Do not count an unverified replacement, or retreat to Earth supply, as proof of continued 0B production.
For options passing those requirements, use these swing weights:
| Criterion | Weight | Range being valued and justification |
|---|---|---|
| C1. Avoid unsupported irreversible commitment | 45% | From committing with an unproven indispensable function to requiring demonstrated capability or a qualified substitute. This is the largest swing because failure can invalidate the entire 0B investment. |
| C2. Avoid unnecessary qualification cost and delay | 25% | From forcing every implementation to TRL 6 regardless of replaceability to qualifying only what the selected production architecture actually needs. This materially affects the cost and duration of 0A. |
| C3. Auditability and enforceability | 20% | From unresolved labels and discretionary exceptions to a reproducible dependency-and-evidence test. A gate rule has little value if it can be reinterpreted at commitment. |
| C4. Preserve useful architecture options | 10% | From locking one implementation prematurely to allowing demonstrated substitutes without weakening functional assurance. Important, but subordinate to protecting the irreversible decision. |
These are proposed owner value judgments, not empirically measured constants.
3. Options
A. Null: retain the split and current interim holds.
Argument for: avoids premature classification and preserves the existing conservative TRL 6 holds.
Reject: the split remains unresolved, T26 remains ambiguous, and development teams cannot reliably plan qualification scope.
B. Permanently classify all eight as project-ending.
Argument for: simple, conservative, and resistant to optimistic fallback claims.
Reject: confuses essential functions with replaceable implementations, especially for T26, and may impose avoidable bespoke qualification.
C. Evidence-conditioned classification, with seven project-ending and bounded T26 closure. — Recommended.
Argument for: protects indispensable capabilities while making declassification depend on demonstrated, affordable alternatives rather than opinion.
D. Classify all eight as architecture-change unless impossibility of substitution is proven.
Argument for: maximises flexibility and initially reduces qualification burden.
Reject: reverses the burden of proof. Proving that no imaginable alternative exists is infeasible; the relevant question is whether a usable alternative has actually been established.
4. Assessment matrix
Scores are ordinal judgments, 1 = poor and 5 = strong. Weighted totals structure the debate; they are not probabilities or measured benefits.
| Option | C1: Commitment protection 45% | C2: Cost/delay 25% | C3: Auditability 20% | C4: Options 10% | Weighted score / 5 |
|---|---|---|---|---|---|
| A. Retain split | 3 | 2 | 1 | 3 | 2.35 |
| B. All eight permanently project-ending | 5 | 1 | 4 | 1 | 3.55 |
| C. Evidence-conditioned ruling | 5 | 3 | 4 | 5 | 4.30 |
| D. All architecture-change | 1 | 4 | 2 | 5 | 2.40 |
Recommended technology rulings
| Technology | Ruling | Reason; evidence that could change it |
|---|---|---|
| T02: MW-scale deployable arrays | Project-ending | Selected tug/site power architecture depends on power at scale. Declassify only after an alternative closes power, deployment, mass, thermal and transport budgets at accepted production throughput. “Use smaller arrays” alone is not evidence. |
| T10: Long-duration autonomy | Project-ending | Intermittently supervised operations must sustain production and manage hazardous states. A less autonomous alternative must demonstrate workload, latency tolerance, safe recovery and communications dependence—not merely nominal teleoperation. |
| T14: Large-scale propellant storage/feed | Project-ending | Propellant delivery is integral to tug performance. Alternate propellant, tanking or mission staging must close feed behaviour, storage losses as applicable, mass, transfer cadence and delivered-cargo performance. |
| T15: Site power generation/transfer | Project-ending | Mining and processing require an integrated power service. Reclassification requires demonstrated operating power, duty cycle, distribution and fault recovery for the selected site—not source nameplate power alone. |
| T22: Product consolidation, packaging, qualification | Project-ending | Producing material is insufficient if it cannot be accepted, transported and used. A simpler product form could change the ruling, but requires an agreed acceptance specification and qualified handling/transport chain. |
| T24: Dust-tolerant mechanisms/seals | Project-ending | Common environmental failures could disable multiple production functions. Demonstrated dust exclusion, reduced mechanism dependence, or replaceable short-life modules could justify reclassification if logistics and maintenance close. |
| T25: Local/node navigation and control | Project-ending | Safe acquisition, approach and cargo exchange are indispensable to the selected logistics chain. Alternate nodes, cooperative aids or supervised operations must demonstrate capture margins, abort behaviour, traffic capacity and outage tolerance. |
| T26: Communications/resilient command | Architecture-change, bounded by rq-0-64 closure | Retain the existing owner ruling provisionally. By KDP-0A, demonstrate that loss of the proposed implementation permits a qualified alternative service and tolerable disconnected operation. Otherwise automatically elevate to project-ending. |
A technology ID may contain both essential and replaceable elements. Split the requirement where necessary; do not let a broad label hide an unqualified essential function.
5. Sensitivity vs trade-off points
Sensitivity points—facts that can change the ruling
- Minimum authorised production: lower throughput may make smaller power systems, batch processing or slower logistics viable.
- Disconnected endurance: affects T10, T25 and T26 together.
- Maintenance concept: replaceable modules could reduce T24 life requirements, but increase spares and transport demand.
- Product acceptance requirements: directly determine T22’s qualification burden.
- Common-cause independence: a backup sharing the same software, power system or geometry may not provide meaningful substitution.
Trade-off points—owner values, not facts to discover
- How much production reduction is acceptable to preserve 0B?
- How much additional 0A cost and delay is worth reducing irreversible exposure?
- How much staffing and recurring communications expenditure is acceptable in exchange for reduced autonomy?
Recommendation sensitivity: Option C’s advantage over B depends on its evidence process being enforceable. If the programme cannot independently review fallback claims or control requirements changes, B becomes the safer operational policy.
6. Evidence certainty
These are adapted GRADE judgments, not formal clinical-style evidence reviews. The available record is the supplied synthesis of gates.md, gates-proposal.yaml, trl-baseline.yaml and decisions.md; no supporting test reports or costed fallback studies were provided.
| Key claim | Evidence certainty | Analytic confidence; likelihood |
|---|---|---|
| D-01/D-02 establish the stated real-option and no-waiver principles | High within the supplied decision record | High confidence in the policy interpretation; not a probabilistic claim. |
| The seven proposed project-ending technologies support indispensable production functions | Moderate | Moderate confidence from functional dependencies; architecture-specific substitution remains unresolved. |
| No admissible fallback has yet been established for those seven | Low | High confidence that none is demonstrated in this record; low confidence about whether undisclosed work exists. |
| T26 can remain architecture-change without weakening 0B assurance | Low | Conditional judgment only; depends on service alternatives and disconnected operations evidence. |
| Evidence-conditioned classification will reduce unnecessary qualification spending | Low | Plausible benefit, but magnitude and likelihood cannot be estimated from the supplied material. |
The panel’s TRL spreads are not probability distributions. In particular, T26’s competing maturity assessments require a common unit of assessment: component, link, or integrated command service.
7. Key assumptions
| Assumption | Evidence that would falsify it |
|---|---|
| 0B production requires the functions represented by the seven project-ending technologies | A controlled production architecture that removes a function while satisfying authorised output, safety, licence and economics constraints. |
| No currently evidenced fallback warrants lower classification | An independently reviewed fallback package with relevant demonstrations, resources, interfaces and executable transition plan. |
| T26’s implementation can potentially be substituted without losing the production mission | Evidence of unavoidable command dependence, inadequate communications alternatives, or failure of safe disconnected operation. This would trigger elevation. |
| TRL demonstrations can be scoped meaningfully to the selected architecture | Findings that interactions, duration or scale effects are not represented by the proposed demonstration; the verification scope must then expand. |
ACH ranking, least disconfirmed first:
- Essential functions with potentially replaceable implementations—best fits the functional dependencies and classification disagreements.
- Every listed implementation is indispensable—possible, but too strong without architecture-level fallback analysis.
- All eight have readily usable alternatives—least supported; no qualifying fallback packages are presented.
This ranks hypotheses by current contradiction, not numerical probability.
8. Decision, warrant, accepted downside
Adopt Option C and insert this rule into the gate proposal:
A technology is project-ending where failure of its required capability leaves no evidenced alternative preserving authorised 0B production within approved safety, licence, performance, schedule and cost limits. Unproven alternatives do not justify lower classification. Project-ending technologies shall achieve TRL 6 in the relevant environment before KDP-0B, without waiver.
Reclassification requires owner approval of an independently reviewed fallback package identifying the replacement, qualification evidence, integrated budgets, transition resources, dependencies and common-cause vulnerabilities. A fallback requiring an unqualified project-ending technology is inadmissible.
T26 retains rq-0-64’s architecture-change ruling until KDP-0A. Failure to demonstrate survivable substitution or disconnection by that review automatically makes the affected capability project-ending.
Warrant: failure consequences and reversibility—not panel vote counts, current TRL or generic technological familiarity—determine required assurance.
Accepted downside: additional 0A analysis and testing, and potentially a delayed or rejected 0B commitment. This is preferable to discovering after commitment that an “architecture change” is actually a new production programme.
9. Consequences
- Owner: approve the classifications and define acceptable fallback performance/cost boundaries at KDP-0A.
- Technology leads: produce function-specific qualification plans and bounded fallback packages.
- Systems engineering: maintain dependency and common-cause analyses, especially across power, autonomy, navigation and communications.
- Gate authority: assess the selected integrated service, not merely mature components; architecture-change status is not blanket permission for immature critical functions.
- Programme control: preserve “0A only, Earth supply” as the exit if KDP-0B fails. Target, demand, economics and licence gates remain independent.
Y-statement: In the context of a funded 0A capability programme and optional 0B production commitment, facing unresolved classifications and unevidenced fallbacks, we chose seven project-ending classifications and a time-bounded architecture-change ruling for T26, to protect irreversible investment while permitting demonstrated substitution, accepting additional 0A qualification effort.
Warrant and qualifier: indispensable production functions require demonstrated capability before commitment; these classifications remain revisable only when architecture-specific evidence establishes a credible alternative. This enables qualification planning and rq-0-64 closure, while constraining KDP-0B from proceeding on optimistic substitution claims.
Vote Breakdown
Termination Votes
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Organizational Infrastructure
- Question ID
- rq-0-65
- Created
- 2026-10-18
- Related BOM Items
- bom-0-7