How far have space and process technologies been extrapolated from test to flight or plant, and where did scale-up fail?
Background
rq-0-71 left three positions on how far a TRL 6 test may be extrapolated: a 10× default with a 100× hard limit (Claude), no fixed limit when governing regimes match (Gemini), and a test-supported envelope with no universal ratio (GPT). On duration and wear: numerical runtime rules (Claude), ≤ 10× extrapolation with ≥ 10% of design life tested (Gemini), and validated degradation mechanisms (GPT). Each model rated its own numbers as low confidence. Nobody produced base rates.
Feeds decision-sheet items 2.12, 2.13 and the scale part of 2.19.
Why This Matters
Most project-ending technologies need MW-class power or kt/yr throughput that no facility reaches. The limit decides the size and cost of pathfinders.
How this gets answered
- Literature — Build a case set of scale-ups: the article tested, the article flown or built, the ratio in power, throughput and duration, and whether performance or life fell short.
- Analysis — Shortfall rate against extrapolation ratio and against whether the governing regime changed. Test whether a fixed ratio or a regime test separates successes from failures better.
Research Directions
- Electric propulsion: the NSTAR, NEXT and AEPS lineage; 100 kW-class nested-channel Hall tests; life-test vs flight-life records.
- Space power and structures: array scale-ups (ISS arrays, roll-out arrays), deployables.
- Process plants: first-of-a-kind plant performance against pilot plants, e.g. the RAND pioneer-plant study (Merrow et al.) and later chemical-engineering scale-up reviews.
- Wear and life: accelerated-life-test practice and physics-of-failure validation, and cases where acceleration models failed.
- Report base rates with their uncertainty, and the regime variables that predicted failure.
Owner decides afterwards: how much false-rejection risk (larger pathfinders) to accept in return for protection at the one-way gate.
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Organizational Infrastructure
- Question ID
- rq-0-78
- Created
- 2026-10-20
- Related BOM Items
- bom-0-7bom-0-4