Which BOM line owns programme management, systems engineering and mission assurance, and how long is 0A?
Decision High
wbsprogramme-managementschedulegovernance
Background
All three models exclude programme management, systems engineering and mission assurance (PM/SE/MA) from bom-0-7. No other line claims it, and Claude rates it the largest unowned scope risk. Separately, operations prices 0A at about 4–5.5 years, while the D-02 KDP-0B window puts it at 6–15 (CI-27).
Why This Matters
PM/SE/MA is typically 10–15% of a space programme, so leaving it out biases every total low. The 0A length drives the run-rate lines and the A4 check (rq-0-84).
How this gets answered
- Engineering decision: A WBS dictionary entry for PM/SE/MA with a cost basis (percentage of development or a staffing plan), and an approved planning length for 0A that the run-rate lines use.
Research Directions
- Placement options: a new line, inside bom-0-11, or split across items.
- Cost basis from comparable programmes.
- A planning 0A length, consistent with rq-0-63.
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Organizational Infrastructure
- Question ID
- rq-0-87
- Created
- 2026-10-25
- Related BOM Items
- bom-0-7bom-0-10bom-0-11bom-0-17
Related Questions
Governance structure for multi-century, volunteer-driven global coordination
critical - open
Post-scarcity economic valuation frameworks for self-replicating systems
medium - open
Integrated schedule for Phase 0A, the gates and the 0B ramp
high - investigating
What should the TRL rating of deep-space communications and command (T26) assess?
high - answered
Which risk class should apply to the eight technologies the panel split on (T02, T10, T14, T15, T22, T24, T25, T26)?
high - investigating