Open

Which BOM line owns programme management, systems engineering and mission assurance, and how long is 0A?

Decision High
wbsprogramme-managementschedulegovernance

Background

All three models exclude programme management, systems engineering and mission assurance (PM/SE/MA) from bom-0-7. No other line claims it, and Claude rates it the largest unowned scope risk. Separately, operations prices 0A at about 4–5.5 years, while the D-02 KDP-0B window puts it at 6–15 (CI-27).

Why This Matters

PM/SE/MA is typically 10–15% of a space programme, so leaving it out biases every total low. The 0A length drives the run-rate lines and the A4 check (rq-0-84).

How this gets answered

  • Engineering decision: A WBS dictionary entry for PM/SE/MA with a cost basis (percentage of development or a staffing plan), and an approved planning length for 0A that the run-rate lines use.

Research Directions

  1. Placement options: a new line, inside bom-0-11, or split across items.
  2. Cost basis from comparable programmes.
  3. A planning 0A length, consistent with rq-0-63.

Question Details

Question ID
rq-0-87
Created
2026-10-25
Related BOM Items
bom-0-7bom-0-10bom-0-11bom-0-17