Must T11, T18, T09, T12 and T20 be at TRL 6 at KDP-0B?
Background
The Phase 0 TRL re-baseline (work package WP-A, reconciliation/phase-0/trl/) has produced a gate proposal under owner decision D-02: three programme decisions (KDP-0A, a 0A mid-term review, KDP-0B), four discriminating gates TRL cannot express (target, demand, economics, licence) and pre-committed failure outcomes. The panel (Claude Opus 5.5, Gemini 3.1 Pro, GPT-6.1 Sol) agreed on that structure, on TRL 6 in a relevant environment with no waiver for project-ending technologies at KDP-0B, and on the fallback "0A only, Earth supply". It left eleven choices for the owner. This question is one of them.
D-01 (accepted): fund 0A; hold 0B as a gated real option sized at the gate by signed Phase 1 demand; call Phase 0 a capability programme, not a cost saving. D-02 (accepted): stringency follows reversibility; one-way gates (KDP-0B) need TRL 6 in a relevant environment for project-ending technologies with no waivers; two-way internal 0A milestones need TRL 4–5. Gemini's gate response was brief, so several positions below are Claude against GPT; where Gemini is silent that is not agreement.
Sources: reconciliation/phase-0/trl/round-1/gates/synthesis/gates.md, gates-proposal.yaml, trl-baseline.yaml, reconciliation/phase-0/decisions.md.
What the panel said
Project-ending classification for KDP-0B
Agreed core (all three models): T01, T02, T03, T04, T05, T08, T10, T14, T15, T16, T19, T21, T22, T24.
Disputed members:
| Technology | Claude | Gemini | GPT |
|---|---|---|---|
| T25 | Project-ending (split; ruling due at KDP-0A) | Project-ending | TRL 6 as "selected reference implementation," grouped with T09, T12, T20 |
| T26 | Claude's view: project-ending for integrated fleet command. Owner ruling is architecture-change, "possibly project-ending." Open in rq-0-64. | Not listed | TRL 6 integrated service at KDP-0B |
| T18 | 0A flight technology (TRL 6 at scout PDR) | Project-ending | TRL 6 technology maturity before KDP-0B |
| T11 | 0A flight technology | In prose list; absent from YAML | TRL 6 technology maturity before KDP-0B |
| T09, T12, T20 | Architecture-change: TRL ≥ 5, waiverable, with a funded path to 6 | Not listed | TRL 6 for selected implementations; substitutions reassessed |
Split classes needing an owner ruling (Claude's list): T02, T10, T14, T15, T22, T24, T25, T26. Claude holds these at TRL 6, no waiver, until they are ruled on.
| Technology | Claude | Gemini | GPT | Panel headline |
|---|---|---|---|---|
| T11 Rendezvous scout spacecraft (with sampling per Gemini and GP | TRL 3–4, AD² 6, architecture-change | TRL 3–4, AD² 5, architecture-change | TRL 2–3, AD² 6, project-ending | TRL 2–4, project-ending |
| T18 Subsurface sampling and in-situ bulk grade assay | TRL 3–4, AD² 6, project-ending | TRL 3–4, AD² 6, project-ending | TRL 2–3, AD² 6, project-ending | TRL 2–4, project-ending |
| T09 High-voltage power tethers and site distribution on regolith | TRL 2–3, AD² 5, architecture-change | TRL 3–4, AD² 6, architecture-change | TRL 2–3, AD² 5, architecture-change | TRL 2–4, architecture-change |
| T12 Autonomous handling, docking and transfer of 150-300 t paylo | TRL 2–3, AD² 6, architecture-change | TRL 3–4, AD² 5, architecture-change | TRL 2–3, AD² 5, architecture-change | TRL 2–4, architecture-change |
| T20 Distributed energy storage (GPT: and microgrid power managem | TRL 3–5, AD² 4, architecture-change | TRL 3–4, AD² 4, architecture-change | TRL 3–4, AD² 5, architecture-change | TRL 3–5, architecture-change |
Why This Matters
These five sit outside the agreed project-ending core. Scouts (T11) and sampling (T18) are 0A flight technologies whose maturity is settled by their own missions; T09, T12 and T20 are supporting systems Claude would let pass at TRL ≥ 5 with a waiver and a funded path, while GPT wants TRL 6 for the selected implementations.
Key Considerations
- Whether a 0A flight technology belongs in the KDP-0B list at all.
- What 'selected reference implementation' means for the gate.
- Waiver conditions, if any.
Research Directions
- Decide the ruling, with the criteria stated first and the null option (leave the panel's split as is) assessed.
- State the gate criterion or rule text that follows from it.
- Name the evidence that would change the ruling.
Status (2026-10-20)
The owner confirmed the converged part (G-1.8 in reconciliation/phase-0/trl/gate-rulings.yaml). The deliberation could not settle the rest: the positions turn on evidence nobody supplied, and on practice the panel was not given. The open choices (decision sheet reconciliation/phase-0/trl/gate-rulings-sheet.md) are routed to evidence questions: rq-0-77, rq-0-80. This question stays open until they report; then the owner rules, or the panel deliberates again with that evidence.
Multi-Model Discussion
ConcludedRound Winners
Discussion Conclusion
Synthesized by GPT-6.1 SolSummary
All three models rejected a blanket requirement that all five technologies receive a new TRL-6 demonstration at KDP-0B. Claude Opus 5.5, Gemini 3.1 Pro and GPT-6.1 Sol supported using applicable 0A mission evidence for T11/T18 and distinguishing supporting implementations from project-ending dependencies. All three rejected leaving the panel split unresolved. Their mutual approvals of Claude’s and GPT’s responses establish support for those approaches, but not convergence on identical gate text.
The remaining disagreement concerns T18’s binding criterion and the strength of exceptions for T09, T12 and T20. Claude retained T18 as project-ending and required target-specific in-situ bulk-grade evidence; Gemini assessed T18 through its 0A mission rather than a separate pre-gate TRL requirement; GPT required TRL 6 for the relevant sampling-and-assay capability plus acceptable target-specific results. For T09/T12/T20, Claude proposed TRL 6 by default, with TRL-5 exceptions backed by qualified TRL-6 fallbacks and joint-fallback economics. Gemini allowed TRL 5 with an approved waiver, defined fallback and funded maturation plan. GPT tied TRL 6 to irreversible dependency, permitting lower maturity only where independently demonstrated substitution or deferral protects the authorised investment case.
Claude and GPT expressly treated fallback adequacy as unproven; both required the affected item to revert to TRL-6 treatment when the exception’s evidence is insufficient. Gemini expressed greater confidence in substitutability, which Claude and GPT challenged as unsupported. No response established that any particular fallback already qualifies.
Decision record
Claude Opus 5.5: differentiated gates with qualified-fallback exceptions
Y-statement: In the context of D-01’s gated real option and D-02’s one-way KDP-0B gate, facing disputed classifications and potentially cumulative waiver exposure, Claude chose to retain T18 as project-ending with target-specific in-situ assay evidence, remove T11 from the KDP-0B list unless Phase 1 inherits its hardware or software, and require TRL 6 for T09/T12/T20 unless a qualified-fallback exception is earned, to protect the irreversible commitment without unnecessarily blocking substitutable implementations, accepting fallback-qualification expenditure, potentially worse Phase 1 economics, and a gate date dependent on scout assay return.
- Warrant — Claude: The gate should test the consequence of failure; target evidence addresses T18’s risk, while qualified alternatives can address architecture-change risk.
- Qualifier — Claude: A TRL-5 exception requires a named TRL-6 fallback, passing economics with all waived items on their fallbacks simultaneously, fallback penalties in the baseline, and independent waiver authority.
- Accepted downside — Claude: Phase 1 may use a costlier fallback; absent qualifying evidence, the item requires TRL 6 without an exception.
Gemini 3.1 Pro: mission-evidence assessment and tiered exemption
Y-statement: In the context of defining KDP-0B criteria, facing a split over five technologies outside the agreed core, Gemini chose to assess T11/T18 through their 0A mission evidence and permit T09/T12/T20 at TRL 5 with an approved waiver, defined fallback and fully funded maturation plan, to preserve schedule realism and architectural flexibility, accepting the possibility of expensive Phase 1 redesign.
- Warrant — Gemini: 0A flight technologies mature through their missions, while architecture-change technologies can be substituted rather than treated as project-ending.
- Qualifier — Gemini: Its recommendation depends on scout evidence arriving before KDP-0B and on supporting-system failures remaining manageable through alternatives.
- Accepted downside — Gemini: A waived technology may require costly redesign. Gemini also identified T18’s necessity to the economic case as a sensitivity that could invalidate its preferred exemption.
GPT-6.1 Sol: dependency-based gate with inherited evidence
Y-statement: In the context of D-01 and D-02, facing disputed labels and potentially irreversible dependencies, GPT chose capability-based TRL-6 gating with applicable inherited 0A evidence and independently demonstrated reversibility, to protect the investment case without duplicate maturation, accepting additional assurance work and the possibility that all five ultimately require TRL 6.
- Warrant — GPT: Irreversibility, rather than technology-list membership or selection alone, determines required stringency.
- Qualifier — GPT: An unproven substitution defaults to TRL-6 treatment. Lower-maturity acceptance requires a funded, scheduled, interface-compatible alternative or deferral preserving demand, economics, safety and licensing.
- Accepted downside — GPT: The rule requires judgment, dependency analysis and explicit commitment controls rather than a simple fixed list.
Decision-quality audit
Round 1 — Claude Opus 5.5
- Weakest link named in votes: Claude and GPT named information; Gemini named none.
- Composite Scaffold support: Claude and GPT’s votes recognised criteria-before-options, null options, sensitivity analysis, falsifiable assumptions and concrete gate text. Their reservations concerned speculative maturity forecasts, possible fallbacks and the unconfirmed interpretation that current target-gate text permits remote-sensing-only evidence.
- Missing or unsupported elements identified: No voter identified a missing scaffold step. Claude and GPT identified evidence gaps within the information and certainty steps; approval did not establish the forecasts or fallback feasibility as facts.
- Values trade-off identified by Claude: Waiting for the preferred implementation versus accepting a costlier qualified fallback; spending Phase 0 resources on primary maturation versus fallback qualification.
Round 1 — Gemini 3.1 Pro
- Weakest links named in votes: Claude and GPT named reasoning; Gemini named alternatives. All three votes were neutral.
- Composite Scaffold support gaps identified by Claude/GPT: Gemini selected its tiered exemption without resolving its own T18 sensitivity. Claude noted that Gemini’s matrix favoured the hybrid on risk containment without a demonstrated aggregation supporting the final choice. Both challenged high confidence in substitutability and the absence of combined-fallback economics.
- Missing or unsupported elements identified by Gemini: Gemini’s self-review cited insufficient null-option evaluation and no rigorous competing-hypotheses analysis.
- Values trade-off identified by Gemini: Schedule realism and flexibility versus stronger pre-commitment risk containment. Claude and GPT’s objections also concerned missing evidence, not merely different values.
Round 1 — GPT-6.1 Sol
- Weakest link named in votes: Claude and GPT named commitment; Gemini named none.
- Composite Scaffold support: The votes recognised non-compensable requirements, criteria-before-options, a null option, qualified evidence ratings, falsifiable assumptions and a default-to-TRL-6 rule.
- Missing or unsupported elements identified: No voter identified a missing scaffold step. Claude described the commitment as less concrete because its application could still require TRL 6 for all five; GPT acknowledged judgment remains over sufficient alternative maturity.
- Values trade-offs identified by GPT: Demonstration expenditure versus conditional authorisation, deployment delay versus flexibility, and the amount of bounded rework risk acceptable after project-ending exposure is excluded.
Key Points
- All three models: No uniform, duplicate TRL-6 demonstration requirement is justified solely by these five technology identifiers.
- All three models: Leaving the split unresolved is not an acceptable gate policy.
- Claude and GPT: T18’s technological maturity cannot substitute for adequate selected-target evidence.
- Claude: T18 must supply in-situ bulk-grade evidence; ground TRL 6 alone is insufficient.
- Gemini: T11/T18 should be assessed through 0A mission data rather than a separate pre-gate TRL rule.
- Claude and GPT: Applicable 0A evidence should be reused, although Claude’s T11 re-entry trigger is hardware/software inheritance and GPT’s is an outstanding critical capability.
- Claude and GPT: A funded maturation plan alone does not establish that Phase 1 survives implementation failure.
- Claude: Multiple exceptions must pass a simultaneous joint-fallback economics case.
- GPT: Exceptions must remain reversible through explicit substitution deadlines and automatic stop triggers.
- All three models: Their proposed flexibility does not authorise a waiver for a genuinely project-ending dependency under D-02.
Unresolved Questions
- T18’s exact criterion: Claude requires target-based in-situ bulk assay; GPT requires applicable TRL 6 plus acceptable target evidence; Gemini relies on mission evidence. The panel did not agree identical wording.
- T11’s return to the gate: Claude uses Phase 1 hardware/software inheritance; GPT uses continuing critical dependency. Gemini did not specify an equivalent re-entry rule.
- Exception strength: Claude requires TRL-6 fallbacks and joint-fallback economics; Gemini proposes a defined fallback and funded maturation; GPT requires independently demonstrated reversibility without Claude’s explicit universal fallback-TRL threshold.
- Fallback feasibility: Claude and GPT identify this as unevidenced; Gemini’s higher confidence was challenged in the votes.
- Reference implementation: Claude binds it to the frozen design and operating scope; GPT binds it to the configuration underpinning the approved architecture, models, interfaces and qualification plan. The precise shared definition remains unwritten.
- Owner preferences: Claude and GPT identify acceptable delay, fallback expenditure and bounded rework exposure as values decisions rather than facts testing alone can settle.
Recommended Actions
- Following all three models: Replace the unresolved split with explicit gate text before teams rely on it for maturation planning.
- Following Claude and GPT: Require an evidence-applicability record showing which 0A demonstrations satisfy which KDP-0B capabilities.
- Following Claude and GPT: Confirm the scout payload, assay scope, target-evidence acceptance criteria and delivery date; inspect the actual target-gate text before accepting Claude’s proposed remote-sensing loophole as established.
- Following Claude: Commission named fallback trades for T09/T12/T20 and test simultaneous fallback economics, carrying penalties in the baseline.
- Following GPT: Map irreversible commitments, substitution deadlines, interface constraints and automatic stop triggers.
- Following Claude and GPT: Default affected dependencies to TRL 6 when exception evidence is inadequate; do not treat proposed alternatives as qualified.
- Following the distinctions identified by all three: Ask the owner to settle T18 wording, T11 re-entry and exception thresholds explicitly, while recording schedule-versus-assurance preferences.
- Following GPT: Preserve the pre-committed “0A only, Earth supply” outcome if required evidence is unavailable.
questionId: "rq-0-66"
topics:
- id: blanket-trl-six
topic: Blanket TRL-6 requirement for all five technologies
positions:
- statement: Reject a uniform duplicate demonstration requirement; reuse applicable 0A evidence and distinguish dependencies.
models: ["Claude Opus 5.5", "Gemini 3.1 Pro", "GPT-6.1 Sol"]
evidence: "All three rejected blanket treatment and the unresolved null option in Round 1."
resolution_status: resolved
priority: high
- id: t18-gate-criterion
topic: Binding requirement for T18
positions:
- statement: Retain project-ending status and require selected-target in-situ bulk-grade evidence; ground TRL 6 alone is insufficient.
models: ["Claude Opus 5.5"]
evidence: "Claude's proposed target-evidence provenance rule and no-waiver requirement."
- statement: Assess T18 through 0A mission evidence rather than a separate pre-gate TRL requirement.
models: ["Gemini 3.1 Pro"]
evidence: "Gemini's tiered exemption, conditional on scout evidence supporting the gate."
- statement: Require TRL 6 for the applicable sampling-and-assay capability plus acceptable target-specific results.
models: ["GPT-6.1 Sol"]
evidence: "GPT's distinction between capability maturity and target adequacy."
resolution_status: partially-resolved
priority: critical
- id: t11-evidence-and-reentry
topic: T11 evidence inheritance and return to KDP-0B
positions:
- statement: Remove T11 from the list unless Phase 1 inherits its hardware or software.
models: ["Claude Opus 5.5"]
evidence: "Claude's explicit inheritance-based re-entry condition."
- statement: Assess T11 through its 0A mission data.
models: ["Gemini 3.1 Pro"]
evidence: "Gemini's classification of T11 as a self-proving 0A flight technology."
- statement: Reuse applicable 0A evidence and require TRL 6 for outstanding scout capabilities critical to 0B.
models: ["GPT-6.1 Sol"]
evidence: "GPT's configuration-applicability and continuing-dependency tests."
resolution_status: partially-resolved
priority: high
- id: supporting-system-exceptions
topic: Exceptions for T09, T12 and T20
positions:
- statement: Default to TRL 6; permit TRL 5 only with TRL-6 fallbacks, joint-fallback economics, baseline penalties and independent authority.
models: ["Claude Opus 5.5"]
evidence: "Claude's waiver-stacking analysis; fallback feasibility remains conditional."
- statement: Permit TRL 5 with an approved waiver, defined fallback and fully funded maturation plan.
models: ["Gemini 3.1 Pro"]
evidence: "Gemini's architecture-change classification; Claude and GPT challenged its confidence in substitutability."
- statement: Require TRL 6 for irreversible dependencies; otherwise permit TRL 5 only with independently demonstrated substitution or deferral and commitment controls.
models: ["GPT-6.1 Sol"]
evidence: "GPT's dependency rule, stop triggers and default to TRL 6 when reversibility is unproven."
resolution_status: partially-resolved
priority: critical
Key Points of Agreement
- All three models:** No uniform, duplicate TRL-6 demonstration requirement is justified solely by these five technology identifiers.
- All three models:** Leaving the split unresolved is not an acceptable gate policy.
- Claude and GPT:** T18’s technological maturity cannot substitute for adequate selected-target evidence.
- Claude:** T18 must supply in-situ bulk-grade evidence; ground TRL 6 alone is insufficient.
- Gemini:** T11/T18 should be assessed through 0A mission data rather than a separate pre-gate TRL rule.
- Claude and GPT:** Applicable 0A evidence should be reused, although Claude’s T11 re-entry trigger is hardware/software inheritance and GPT’s is an outstanding critical capability.
- Claude and GPT:** A funded maturation plan alone does not establish that Phase 1 survives implementation failure.
- Claude:** Multiple exceptions must pass a simultaneous joint-fallback economics case.
- GPT:** Exceptions must remain reversible through explicit substitution deadlines and automatic stop triggers.
- All three models:** Their proposed flexibility does not authorise a waiver for a genuinely project-ending dependency under D-02.
Unresolved Questions
- T18’s exact criterion:** Claude requires target-based in-situ bulk assay; GPT requires applicable TRL 6 plus acceptable target evidence; Gemini relies on mission evidence. The panel did not agree identical wording.
- T11’s return to the gate:** Claude uses Phase 1 hardware/software inheritance; GPT uses continuing critical dependency. Gemini did not specify an equivalent re-entry rule.
- Exception strength:** Claude requires TRL-6 fallbacks and joint-fallback economics; Gemini proposes a defined fallback and funded maturation; GPT requires independently demonstrated reversibility without Claude’s explicit universal fallback-TRL threshold.
- Fallback feasibility:** Claude and GPT identify this as unevidenced; Gemini’s higher confidence was challenged in the votes.
- Reference implementation:** Claude binds it to the frozen design and operating scope; GPT binds it to the configuration underpinning the approved architecture, models, interfaces and qualification plan. The precise shared definition remains unwritten.
- Owner preferences:** Claude and GPT identify acceptable delay, fallback expenditure and bounded rework exposure as values decisions rather than facts testing alone can settle.
Recommended Actions
- Following all three models:** Replace the unresolved split with explicit gate text before teams rely on it for maturation planning.
- Following Claude and GPT:** Require an evidence-applicability record showing which 0A demonstrations satisfy which KDP-0B capabilities.
- Following Claude and GPT:** Confirm the scout payload, assay scope, target-evidence acceptance criteria and delivery date; inspect the actual target-gate text before accepting Claude’s proposed remote-sensing loophole as established.
- Following Claude:** Commission named fallback trades for T09/T12/T20 and test simultaneous fallback economics, carrying penalties in the baseline.
- Following GPT:** Map irreversible commitments, substitution deadlines, interface constraints and automatic stop triggers.
- Following Claude and GPT:** Default affected dependencies to TRL 6 when exception evidence is inadequate; do not treat proposed alternatives as qualified.
- Following the distinctions identified by all three:** Ask the owner to settle T18 wording, T11 re-entry and exception thresholds explicitly, while recording schedule-versus-assurance preferences.
- Following GPT:** Preserve the pre-committed “0A only, Earth supply” outcome if required evidence is unavailable.
- id: blanket-trl-six
- statement: Reject a uniform duplicate demonstration requirement; reuse applicable 0A evidence and distinguish dependencies.
- id: t18-gate-criterion
- statement: Retain project-ending status and require selected-target in-situ bulk-grade evidence; ground TRL 6 alone is insufficient.
- statement: Assess T18 through 0A mission evidence rather than a separate pre-gate TRL requirement.
- statement: Require TRL 6 for the applicable sampling-and-assay capability plus acceptable target-specific results.
- id: t11-evidence-and-reentry
- statement: Remove T11 from the list unless Phase 1 inherits its hardware or software.
- statement: Assess T11 through its 0A mission data.
- statement: Reuse applicable 0A evidence and require TRL 6 for outstanding scout capabilities critical to 0B.
- id: supporting-system-exceptions
- statement: Default to TRL 6; permit TRL 5 only with TRL-6 fallbacks, joint-fallback economics, baseline penalties and independent authority.
- statement: Permit TRL 5 with an approved waiver, defined fallback and fully funded maturation plan.
- statement: Require TRL 6 for irreversible dependencies; otherwise permit TRL 5 only with independently demonstrated substitution or deferral and commitment controls.
Discussion Rounds
Responses
Must T11, T18, T09, T12 and T20 be at TRL 6 at KDP-0B?
Short answer: no, not uniformly. The five do not form one class, and treating them as one is what produces the Claude/GPT split.
- T18 (sampling and assay) stays project-ending at KDP-0B. Its evidence should come from the 0A scout mission itself, which is a higher bar than ground TRL 6.
- T11 (scout spacecraft) leaves the KDP-0B technology list. It returns only under a named re-entry condition.
- T09, T12 and T20 are held at TRL 6 for the selected reference implementation by default. A waiver is allowed only for an item that has a qualified TRL 6 fallback, and only if the economics gate still closes with every waived item on its fallback at the same time.
This position is neither Claude's nor GPT's. I argue it below. Gemini's stated positions are counted only where it actually stated them.
1. Frame & decision type
Decision type. This is a property decision on the KDP-0B gate: what membership and criterion apply to five technologies. Two executive sub-decisions sit inside it: what "selected reference implementation" binds, and what conditions a waiver must meet.
Reversibility.
- The gate text is cheap to change before KDP-0B.
- The gate outcome is not cheap to change. Under D-02, KDP-0B is a one-way door, so the rule must be written as if it will be applied mechanically by people under schedule pressure.
Cynefin domain. Complicated, not complex. The facts that matter are knowable before KDP-0B:
- whether the scouts returned assay data;
- whether a fallback exists for each item;
- whether economics closes with that fallback.
So the decision can be made now and resolved by evidence later. That is the property a real-options gate under D-01 should have.
What is actually being decided. The question as posed asks "TRL 6 or not?". The more useful question is: what failure must KDP-0B protect against for each item, and is TRL 6 the right instrument for it?
- T11 and T18. The risk is committing Phase 1 to a target whose grade was never measured. TRL is a weak proxy for that. The target gate is the real instrument.
- T09, T12 and T20. The risk is committing Phase 1 to an architecture that fails economically if one of these is late or underperforms. TRL 6 is one guard against that. A proven fallback that closes economics is a second, equally valid guard.
2. Criteria and weights
These are swing weights, stated before options. Each weight reflects how much the options differ on that criterion, not how important the topic is in the abstract.
| # | Criterion | Swing range across options | Weight | Why this weight |
|---|---|---|---|---|
| C1 | Protection against an irreversible wrong commitment at KDP-0B | From "a Phase 1 commitment can go through with an unmeasured target or an unfallbacked TRL 4–5 item" to "cannot" | 0.35 | Under D-02 this is the reason the gate exists. The options differ sharply here. |
| C2 | Cost of delay at KDP-0B | From "the gate can slip by more than 12 months waiting on T12 TRL 6" to "no slip from these items" | 0.20 | Real but bounded. D-01 sizes 0B by signed demand, and demand has a shelf life. |
| C3 | Auditability and resistance to gaming | From "a waiver is a promise ('funded path')" to "a waiver is a pass/fail check on stated evidence" | 0.20 | One-way gates fail through erosion more than through bad initial rules. The options differ a lot here. |
| C4 | Consistency with D-01, D-02 and the four discriminating gates | From "duplicates or conflicts with the target and economics gates" to "composes with them" | 0.15 | Matters, but the differences are mostly drafting quality. |
| C5 | Phase 0 resource burden | From "fund TRL 6 campaigns for all five plus fallbacks" to "fund only what the gate needs" | 0.10 | The swing is a few qualification campaigns. It is meaningful but small relative to the 0B commitment. |
A deliberate omission: "agreement with the panel majority" is not a criterion. Per the guidelines, disagreements are kept, not averaged away.
3. Options
Group A: T11 and T18 (0A flight technologies)
- A0 (null). Leave the split as it is.
- Effect: T18 is project-ending (Gemini, GPT, panel headline). T11 is project-ending in GPT's view and the panel headline, absent from Gemini's YAML, and architecture-change in Claude's view.
- Result: the gate text is ambiguous, and whoever drafts the YAML decides.
- A1 (GPT). Both at TRL 6 technology maturity before KDP-0B.
- A2 (Claude). Both treated as 0A flight technology, gated at scout PDR (TRL 6), and absent from the KDP-0B list.
- A3 (recommended).
- T18 stays project-ending at KDP-0B. Its criterion is evidence provenance: the target gate must be satisfied by T18-class measurements made at the target. Ground TRL 6 alone does not satisfy KDP-0B.
- T11 is off the KDP-0B list. It re-enters if any Phase 1 element inherits T11 hardware or software, for example a scout-derived bus for repeat prospecting or a T12 handling vehicle.
Group B: T09, T12, T20 (supporting systems)
- B0 (null). Leave the split. In practice this means GPT's TRL 6 for the drafter who reads the headline, and Claude's TRL ≥ 5 waiverable for the drafter who reads the classification. This is the worst outcome for a one-way gate.
- B1 (GPT). TRL 6 for selected implementations, no waiver. Substitutions trigger reassessment.
- B2 (Claude). TRL ≥ 5, waiverable, with a funded path to TRL 6.
- B3 (recommended): TRL 6 default with a substitution-backed waiver.
- The selected reference implementation must be at TRL 6.
- A waiver down to TRL ≥ 5 is permitted only if all three conditions hold:
- A named fallback implementation is at TRL 6 in a relevant environment.
- The economics gate passes in a joint-fallback case, with every waived item on its fallback simultaneously.
- The fallback's mass, power and schedule penalties are carried in the Phase 1 baseline, not held in reserve.
- B4 (rejected): make them project-ending. This is TRL 6 with no waiver and no fallback route. It differs from B1 only in labelling, and it overstates the consequence of failure. These are architecture-change by unanimous classification.
Why I reject the alternatives
- A1. It asks for ground TRL 6 on technologies that, by KDP-0B, should have flight evidence or should have failed the target gate. The criterion is redundant when the scouts succeed. When they fail it is misleading, because a TRL 6 sampler on the ground does not make an unmeasured target investable. It also puts T11 bus maturity on a gate where it has no decision value.
- A2. It is right about T11 but leaves a gap for T18.
- If the target gate were satisfied by remote sensing alone, which nothing in the current four-gate text forbids, KDP-0B could pass without bulk grade ever being measured in situ.
- Phase 1 site selection also depends on T18-class assay, not just Phase 0.
- Dropping T18 from the list removes its only binding hook.
- B1. It is safe but blunt.
- T12, autonomous handling of 150–300 t payloads, is the item least likely to reach TRL 6 by KDP-0B. Panel estimates are TRL 2–4, with AD² 5–6.
- Under B1 the whole Phase 1 decision waits on T12, even where smaller-payload handling at TRL 6 could carry the architecture at a known cost.
- That turns an architecture-change technology into a project-schedule-ending one, which is the classification error D-02 was meant to avoid.
- B2. It is efficient but not auditable.
- A "funded path to 6" is a budget line, not evidence. It does not answer what happens to Phase 1 if the path fails, and that is the only question a one-way gate should ask.
- Three independent waivers can also stack. Each item is survivable alone, but the joint failure was never tested.
4. Assessment matrix (QOC)
Scores run from 1 (poor) to 5 (best) on each criterion's swing range, weighted per Section 2.
Group A: T11 and T18
| Option | C1 (0.35) | C2 (0.20) | C3 (0.20) | C4 (0.15) | C5 (0.10) | Weighted |
|---|---|---|---|---|---|---|
| A0 null | 2 | 3 | 1 | 2 | 3 | 2.05 |
| A1 GPT | 3 | 3 | 4 | 2 | 2 | 2.95 |
| A2 Claude | 3 | 5 | 3 | 4 | 5 | 3.80 |
| A3 | 5 | 4 | 5 | 5 | 4 | 4.65 |
Rationale for the key cells:
- A3 on C1 (5). It closes the remote-sensing loophole. A2 does not, so A2 scores 3.
- A1 on C4 (2). It duplicates the target gate with a weaker criterion.
Group B: T09, T12, T20
| Option | C1 (0.35) | C2 (0.20) | C3 (0.20) | C4 (0.15) | C5 (0.10) | Weighted |
|---|---|---|---|---|---|---|
| B0 null | 2 | 3 | 1 | 1 | 3 | 1.95 |
| B1 GPT | 5 | 1 | 5 | 3 | 2 | 3.60 |
| B2 Claude | 2 | 5 | 2 | 3 | 4 | 2.95 |
| B3 | 4 | 4 | 4 | 5 | 2 | 3.95 |
| B4 project-ending | 5 | 1 | 5 | 1 | 2 | 3.30 |
Rationale for the key cells:
- B3 on C1 (4, not 5). A fallback at TRL 6 protects against the item failing. It does not protect against the fallback's penalty being underestimated.
- B3 on C5 (2). It requires qualifying fallbacks, which is real money.
- B3 on C4 (5). It makes the economics gate test the architecture-change consequence directly, which is what "architecture-change" means.
Robustness of the Group B ranking. B3's margin over B1 is about 0.35, which is not large.
- If C2 falls below roughly 0.10 and C1 rises to roughly 0.45, B1 wins. This is the trade-off point in Section 5.
- The ranking is robust to any reasonable C3/C4/C5 reweighting.
5. Sensitivity vs trade-off points
Sensitivity points (facts that, once settled, decide the issue)
- S1: When the scouts report relative to KDP-0B.
- If scout assay data reliably arrives before KDP-0B, A3 costs nothing extra.
- If the KDP-0B date is planned before scout return, A3 forces a slip. That is correct: the target gate could not honestly pass anyway. But the owner should see the slip now.
- S2: Whether a TRL 6 fallback exists or can be qualified for T12.
- Plausible fallbacks are smaller handling units (30–60 t class) with more transfers, or crewed or teleoperated assist.
- If no fallback can be qualified, B3 collapses to B1 for T12. That is acceptable and honest.
- S3: Economics margin in the joint-fallback case.
- Example penalties include a lower-voltage T09 with more conductor mass, a smaller-unit T12 with more cycles, and an oversized T20.
- If the margin is thin, B3 effectively forbids the waivers. The rule self-adjusts; the owner does not need to rule twice.
- S4: Whether any Phase 1 element inherits T11. This determines whether T11 re-enters the list.
Trade-off points (values questions for the owner, not facts)
- T-1: Schedule versus one-way safety for T12.
- B3 accepts a Phase 1 that may run on a fallback with a worse cost per tonne, in exchange for not waiting on T12 TRL 6.
- B1 accepts waiting.
- No evidence settles this. It depends on how the owner values a signed-demand window under D-01 against architecture purity. I recommend B3, but this is the owner's call and should be recorded as such.
- T-2: Phase 0 spend on fallbacks versus Phase 0 spend on primaries.
- Money spent qualifying a fallback is not spent advancing the primary.
- This is the "capability programme, not a cost saving" framing of D-01, made concrete.
6. Evidence certainty
Likelihood (how probable) is kept separate from confidence (how good the evidence is). Every TRL estimate here is panel judgment, not test data.
| Claim | Likelihood | Confidence / GRADE | Basis |
|---|---|---|---|
| T18 current TRL is 2–4 | — | Low (three estimates span two levels; no cited test campaigns) | Panel table |
| T12 reaches TRL 6 for 150–300 t by a nominal KDP-0B | Unlikely (~20–35%) | Low | Lowest TRL and highest AD² in the group; no analogue at that payload class in an autonomous surface or proximity context |
| T20 reaches TRL 6 by KDP-0B | Likely (~60–75%) | Medium | Storage cell technology is mature terrestrially. The risk is environment (thermal cycling, dust, radiation) and microgrid management if GPT's scope is used. AD² 4–5 is the lowest in the group. |
| T09 reaches TRL 6 by KDP-0B | About as likely as not | Low | High-voltage distribution over regolith couples arcing, charging and dust; little directly relevant heritage |
| Remote sensing alone could satisfy the current target-gate text | Likely | Medium | Inferred from the gate structure as summarised; worth confirming against gates-proposal.yaml |
| Independent waivers stack into an untested joint failure | Very likely (structural) | High | Follows from B2's text, which contains no joint test |
| Gemini's T11 classification is a drafting inconsistency (prose vs YAML), not a considered position | Likely | Medium | Gemini's response was brief; prose and YAML disagree |
What these probabilities are. They are my judgment, offered as calibrated language so others can disagree in numbers. They are not elicited estimates. Before KDP-0A they should be replaced by a structured elicitation, using Cooke's classical method or SHELF, on T12 and T09 specifically.
7. Key assumptions
| # | Assumption | What would falsify it |
|---|---|---|
| K1 | The 0A scout mission carries a T18-class instrument capable of bulk grade assay | Scout payload definition at 0A mid-term review omits in-situ assay or limits it to surface spectroscopy. A3's provenance rule then cannot be met, and either the scout scope or the target gate must change. |
| K2 | Phase 1 does not reuse T11 hardware or software | Phase 1 concept baseline lists a scout-derived bus for prospecting, tugs or handling. T11 re-enters at TRL 6. |
| K3 | Credible TRL 6 fallbacks exist for T09 and T20, and plausibly for T12 | A fallback trade at 0A mid-term shows no fallback within, say, a 2× penalty on the affected subsystem. That item reverts to B1. |
| K4 | The economics model can represent fallback penalties at subsystem resolution | The economics gate model is top-down (cost per tonne) without subsystem hooks. B3's joint-fallback test becomes unauditable, and B1 is the safer default. |
| K5 | Waivers are granted by an authority independent of the Phase 1 advocate | Decision rights (RAPID) give the 0B programme manager waiver authority. Raise C3 weight; B1 gains. |
Competing hypotheses for why GPT holds TRL 6 on T09, T12 and T20 (ACH)
The test was which hypothesis the panel record disconfirms least.
- H1: Waiver erosion (fewest disconfirmations). GPT distrusts waiver processes at one-way gates. Its "substitutions reassessed" clause targets this.
- B3 answers H1 directly: a waiver becomes a pass/fail check on fallback evidence.
- H2: Fallbacks would not close economics. No disconfirming evidence, but no confirming evidence either. Nobody has run the joint case.
- B3 makes this testable rather than assumed.
- H3: TRL 5 to 6 is a large step for these items. Partially disconfirmed. GPT's own AD² for T09, T12 and T20 is 5, lower than its 6 for T11 and T18. That suggests GPT sees them as less hard, not harder.
If H1 is the real driver, B3 should be acceptable to GPT. If H2 is, the joint-fallback test will vindicate GPT empirically. Either way B3 is the better-structured rule.
8. Decision, warrant, accepted downside
Recommended gate text
Drafted for gates-proposal.yaml:
kdp_0b_technology_criteria:
T18:
class: project-ending
criterion: >
Bulk grade assay of the selected target obtained by a T18-class
instrument operating at the target (TRL >= 7 by flight). Ground TRL 6
alone does not satisfy KDP-0B. The target gate shall not pass on
remote-sensing evidence without T18 in-situ confirmation.
waiver: none
if_phase1_assay_differs_from_scout_instrument: Phase 1 variant at TRL 6
T11:
class: 0A flight technology (not on KDP-0B list)
governed_by: scout PDR, TRL 6
re_entry: >
If any Phase 1 element inherits T11 hardware or software, T11
is added to KDP-0B at TRL 6, class architecture-change.
failure_path: captured by target-gate pre-committed failure outcome
T09, T12, T20:
class: architecture-change
reference_implementation: >
The specific design (operating point, payload class, chemistry and
control scope) named in the Phase 1 configuration baseline frozen at
KDP-0B. Any post-KDP-0B substitution triggers reclassification and
a re-run of the economics gate.
criterion: TRL 6 in a relevant environment for the reference implementation
waiver:
permitted_to: TRL >= 5
all_conditions_required:
- named fallback implementation at TRL 6 in a relevant environment
- economics gate passes in the joint-fallback case
(every waived item on its fallback simultaneously)
- fallback penalties carried in the Phase 1 baseline, not in reserve
- waiver authority independent of the Phase 1 programme office
if_no_qualified_fallback: no waiver (reverts to TRL 6, no waiver)
Y-statement
In the context of a one-way KDP-0B gate under D-02, facing a panel split between "TRL 6 for all five" and "TRL ≥ 5 waiverable for the supporting three, 0A-only for the scouts", we chose to:
- bind T18 to flight-provenance evidence through the target gate;
- remove T11 from the list, with a re-entry condition;
- hold T09, T12 and T20 at TRL 6 with a waiver earned only by a qualified fallback that closes joint-fallback economics,
to achieve a gate that tests the actual irreversible consequence of each technology failing, accepting:
- that Phase 1 may start on a costlier fallback architecture, most likely for T12;
- that Phase 0 must fund fallback qualification;
- that KDP-0B cannot precede scout assay return.
Toulmin structure
- Grounds. All three models classify T09, T12 and T20 as architecture-change. Two of three plus the headline classify T18 as project-ending. T11's classification is inconsistent across sources.
- Warrant. For a one-way gate, the right test of a technology is whether the commitment survives that technology's failure. For architecture-change items, a qualified fallback that closes economics answers this as well as TRL 6 on the primary. For a sampling technology that should already have flown, flight evidence answers it better than ground TRL.
- Backing. D-02's "stringency follows reversibility". The real-options logic of D-01.
- Qualifier. Probably the right rule for T09 and T20 (medium confidence). Plausibly right for T12, low confidence, contingent on S2. Very likely right for T18 and T11.
- Rebuttal conditions. The rule fails if:
- fallback penalties are systematically underestimated (K4);
- waiver authority is captured (K5);
- no T12 fallback exists, in which case B1 holds for T12.
Accepted downside, stated plainly
- A Phase 1 baseline carrying, for example, smaller-unit T12 handling with a cost-per-tonne penalty of unknown size.
- A KDP-0B date that is hostage to scout return.
I would rather slip the gate than pass it on an unmeasured grade.
9. Consequences
Enables
- An economics-gate specification that must include a joint-fallback case. This is new work for the economics gate owner.
- Clean KDP-0B YAML with no drafter-dependent ambiguity. It also resolves the Gemini prose/YAML inconsistency on T11.
- A defined meaning for "selected reference implementation" that the other open choices can reuse, notably T25 and T26 if they land as architecture-change.
Constrains
- 0A mid-term review must deliver:
- the scout payload definition confirming T18-class in-situ assay (K1);
- a fallback trade for T09, T12 and T20 naming fallback implementations and their penalties;
- a structured elicitation of T12 and T09 TRL trajectories.
- Phase 0 budget must carry fallback qualification lines, roughly one campaign each, likely smaller than the primary campaigns.
- The KDP-0B schedule must be set after nominal scout assay return plus analysis margin.
- The target gate text must be amended to forbid a remote-sensing-only pass.
Related open decisions
- T25 and T26. If ruled architecture-change, they inherit B3 and should not get a separate rule.
- Claude's split classes (T02, T10, T14, T15, T22, T24) are unaffected. They stay at TRL 6 with no waiver pending ruling.
Evidence that would change this ruling
- The scout scope excludes in-situ bulk assay. A3 then fails, and the target gate needs an alternative provenance rule.
- The Phase 1 concept reuses T11. T11 then returns at TRL 6.
- The fallback trade shows no TRL 6 fallback for T12 within a tolerable penalty. T12 then reverts to B1, TRL 6 with no waiver. I would accept that without reopening the rule.
- The joint-fallback economics case fails with all three waived. The rule then forbids waivers in practice. B3 converges to B1 empirically, which is the intended behaviour.
- Decision rights put waiver authority inside the Phase 1 programme office. I would then switch my recommendation to B1, because B3's protection depends on independent adjudication.
Vote Breakdown
Termination Votes
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Organizational Infrastructure
- Question ID
- rq-0-66
- Created
- 2026-10-18
- Related BOM Items
- bom-0-7