Does each split technology have a credible, costed fallback that keeps 0B production viable?
Background
The panel split on whether eight technologies are project-ending or architecture-change (rq-0-65: T02, T10, T14, T15, T22, T24, T25, T26), and on the exceptions for T09, T12 and T20 at KDP-0B (rq-0-66). Claude and GPT agree on the test: a technology is project-ending unless an independently reviewed fallback shows a credible, costed, non-common-cause alternative that keeps viable 0B production. Gemini named fallbacks (smaller arrays, localised power, Earth-based packaging, DSN or commercial comms) that no one has costed. The disagreement is about facts nobody has produced.
Feeds decision-sheet items 2.1, 2.2 and 2.4, and the T11 re-entry item under rq-0-66.
Why This Matters
The risk class decides whether a technology must reach TRL 6 with no waiver before KDP-0B. A wrong project-ending label makes the gate stricter than it needs to be. A wrong architecture-change label lets 0B commit on a technology with no real way out.
How this gets answered
- Analysis — One fallback dossier per technology (T02, T09, T10 split into safety and productivity autonomy, T12, T14, T15, T20, T22, T24, T25, T26): the fallback, its own maturity, cost and schedule, common-cause dependencies, and the 0B output and cost per kg with it.
- Simulation — Run the production and cost effect of each fallback through the existing ISRU economics, supply-chain and reliability models (
src/lib/services/simulation/isru-economics,supply-chain,reliability-model.ts), with uncertainty. - Literature — Heritage for each named fallback (e.g. 100 kW-class arrays, storable-propellant tugs, single-craft navigation on Hayabusa2 and OSIRIS-REx, DSN capacity planning).
Research Directions
- A dossier template: fallback, maturity, cost, schedule, common-cause check, effect on 0B output and economics.
- Fill it for each technology; mark where no fallback exists.
- Apply the C+P test to each dossier; report the class it supports and how sensitive that is.
- For T11: does Phase 1 inherit scout hardware or software? If not, T11 drops from the KDP-0B list.
Owner decides afterwards: the boundary for "viable 0B production" (minimum output, maximum cost increase) that each dossier is judged against. D-01's weights are the starting point.
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Organizational Infrastructure
- Question ID
- rq-0-77
- Created
- 2026-10-20
- Related BOM Items
- bom-0-7bom-0-3bom-0-4