What counts as bankable demand for Phase 0 output, and what nameplate capacity does it justify?

Analysis Critical
demand-gateofftakecapacity-sizingeconomics

Background

The owner has ruled that "within 3×" is a quantity ratio and that "signed" demand means specified, financially backed commitments (gate-rulings.yaml G-1.1, G-1.2). Still open from rq-0-68:

  • What backing qualifies. Claude: committed purchase funding, or a costed Earth-supply baseline that would exist if 0B were cancelled, with an independent signatory. Gemini: binding external offtake or a funded internal Phase 1 line item. GPT: independent budget authority, plus counterparty-performance evidence for external demand.
  • Capacity authorised after a pass. Claude: an availability-and-yield cap. Gemini: up to 3× demand. GPT: the smallest feasible configuration.
  • The measurement window.

Feeds decision-sheet items 2.7 and 2.8 and the demand-window item.

Why This Matters

D-01 sizes 0B by signed Phase 1 demand. Loose terms let the project size 0B on hope; tight ones may rule out the only customer, the project's own Phase 1.

How this gets answered

  • Literature — Offtake practice in project finance (take-or-pay, bankability tests, counterparty credit); government anchor-tenant service contracts (NASA COTS, Commercial Crew and CLPS); internal transfer pricing for a captive customer.
  • Simulation — Capacity against demand under uncertain availability, yield and ramp. What do over-capacity (stranded cost) and under-capacity (Earth-supply top-up) cost per sizing rule? Reuses isru-economics and supply-chain.
  • Stakeholder — Project-finance practitioners on whether a captive internal customer can count as bankable demand.

Research Directions

  1. Qualifying-instrument criteria from practice, including how a captive Phase 1 customer is treated.
  2. Expected cost of each sizing rule (Claude, Gemini, GPT) under the rq-0-58 demand range.
  3. A measurement-window rule that stops demand being shifted between periods.

Owner decides afterwards: how much stranded-capacity risk to accept.

Question Details

Question ID
rq-0-81
Created
2026-10-20