Phase 0 → Phase 1 delivery node

Simulation High
logisticsorbitsel1phase-interface

Background

Claude and Gemini pick SEL1 (Gemini cites a 1.5–2.5 km/s each-way penalty from L4/L5); GPT says auto-relocating to L1 is "too strong" and wants joint optimisation with Phase 1, noting L1 needs station-keeping and traffic management. D-04 uses SEL1 as a reference only.

Raised by the Phase 0 re-assessment (round 2, 2026-10-12): reconciliation/phase-0/round-2/reconciliation/phase.md and reconciliation/phase-0/decisions.md.

Why This Matters

Sets tug cadence, the receiving node ($200–600M) and Phase 1 logistics.

How this gets answered

  • Simulation — Joint logistics study: candidate NEAs → candidate nodes (SEL1, SEL4/5, EML1, NEA-local storage) with Phase 1 node location as a variable.

Research Directions

  1. Δv, cadence and traffic per node.
  2. Re-decide at KDP-0B.

Question Details

Source BOM Item
Transport Vehicles
Question ID
rq-0-59
Created
2026-10-12
Related BOM Items
bom-0-4bom-1-4