Decision Gates

Phase 0 is split in two: 0A (research and pathfinders) is funded; 0B (production) is held as an option and exercised only at KDP-0B. The gates below decide whether and when. Stringency follows reversibility: the one-way commitment at KDP-0B needs TRL 6 in a relevant environment with no waivers for project-ending technologies; internal 0A milestones need TRL 4–5. Four discriminating gates test what TRL cannot: the target, demand, economics and the licence.

Months are windows from the start of Phase 0, as the model panel proposed them. Thresholds the owner has not yet ruled on are shown as proposed, with the research question that will settle them.

Gates
11
2 KDPs · 5 reviews · 4 discriminating
Criteria
43
0 met so far (Phase 0 has not started)
Awaiting a ruling
14
criteria · 26 disputed by the panel
Rulings confirmed
8
2 of 5 decisions accepted

Gates

CriterionThreshold (as proposed)TechnologiesStatus
Agreed core project-ending technologies at TRL 6 in relevant environment
TRL 6 exit criterion per technology
TRL 6.All, no waivers
✓ D-02 ⧗ RQ-0-71 ← evidence RQ-0-78,RQ-0-76⧗ RQ-0-72 ← evidence RQ-0-76
Technologies whose project-ending status differs by model
TRL and classification per owner ruling at KDP-0A
TRL 6.T25: project-ending (Claude, Gemini) vs TRL 6 selected implementation (GPT). T26: project-ending (Claude view; open in rq-0-64) vs TRL 6 integrated service (GPT); not listed by Gemini. T18: project-ending (Gemini) vs TRL 6 technology maturity (GPT) vs 0A flight technology (Claude). T11: Gemini prose only; TRL 6 maturity (GPT).
✓ D-02 ⧗ RQ-0-65 ← evidence RQ-0-77⧗ RQ-0-66 ← evidence RQ-0-80
At least one complete metallurgy route end-to-end, routes assessed separately
Feed-to-qualified-product performance (recovery, throughput, reagent losses, waste)
TRL 6.>= 1 route at TRL 6; Claude chain includes T05, T19, T22; GPT includes T05, T22. Gemini sets no KDP-0B metallurgy criterion.
Proposed by Claude, GPT
✓ D-02 ≠ Which technologies make up a complete metallurgy route (Claude includes T19; Gemini sets no criterion)
Power distribution, storage, cargo handling and navigation
TRL of selected implementations with documented scaling
Claude: T09, T12, T20 at TRL >= 5, waiverable, funded path to 6 before 0B CDR. GPT: T09, T12, T20, T25 at TRL 6 for selected implementations; substitutions reassessed.
Proposed by Claude, GPT
✓ G-1.8 ⧗ RQ-0-66 ← evidence RQ-0-77
All four discriminating gates passed for the same configuration
Status of g-target, g-demand, g-economics, g-licence
All passed
Agreed as written
Integrated design closure (mass, power, thermal, reliability, maintenance, logistics, cost, schedule)
Budget margins and reserves
Claude: >= 20% mass, >= 15% power. GPT: closure and reserve policy approved before final review; no unresolved project-ending assumptions.
Proposed by Claude, GPT
≠ Margin and reserve policy (Claude ≥ 20% mass, ≥ 15% power; GPT approves a policy before the review)
Water pilot, only if target is C-type
TRL of water extraction pilot
TRL 5.TRL 5, else drop pilot (Claude); GPT handles in g-water-pilot at TRL 6 and not as a production veto
Proposed by Claude
◐ D-05 interim ≠ TRL 5 and drop the pilot (Claude) vs TRL 6 in a separate release (GPT)
Programme sunset
Month by which KDP-0B must pass
Claude: month 180, fallback executes automatically. GPT: set via rq-0-63; M180 is a planning boundary, not an automatic commitment. Gemini: none.
Proposed by Claude, GPT
✓ G-1.6 ⧗ RQ-0-69 ← evidence RQ-0-83
Pass

Fund 0B at the scale set by signed demand and the delivered-cost model.

Fail

Claude: one slip inside the month-180 sunset, then 0A only, Earth supply, with 0A results archived and published. Gemini: 0A only, Earth supply. GPT: explicit bounded extension, or 0A only, Earth supply.

✓ G-1.6 ⧗ RQ-0-69 ← evidence RQ-0-83

Owner decisions

DecisionRecommendationStatus
D-01 What Phase 0B is for, and when to commitFund 0A. Hold 0B as a gated real option, sized at the gate by signed Phase 1 demand. Call Phase 0 a capability programme, not a cost saving.✓ accepted 2026-10-12
D-02 Gate structure and stringency; use of TRLHybrid: NASA life-cycle gates with TRL/AD² for each critical technology, plus four discriminating gates (target, demand, economics, licence). Stringency follows reversibility.✓ accepted 2026-10-12
D-03 Escaped-debris and containment limitSet an ALARP requirement with an interim design ceiling. The number itself goes to modelling, tests and the licensing state.◐ proposed; interim
D-04 Where Phase 0 delivers its productUse SEL1 as the reference case. Re-decide jointly with Phase 1 at the 0B gate.◐ proposed; interim
D-05 Tug propellant; water-EP trackSelect no propellant yet. Cost iodine as the reference case and argon as the alternate, pending the supply audit and life tests. Water EP stays a desk study until a C-type target is confirmed.◐ proposed; interim

Gate rulings

The panel deliberated eleven open gate rules. The owner confirmed the points where the panel genuinely converged. The rest wait on evidence: each is routed to a research question, and is ruled when that question reports.

Confirmed

  • G-1.1 (rq-0-68) "Within 3×" in the demand gate is a quantity ratio (capacity against signed demand), not a timing tolerance.
  • G-1.2 (rq-0-68) "Signed" demand means specified, financially backed commitments; technical endorsements and planning allowances do not count.
  • G-1.3 (rq-0-70) After a failed licence gate, at most one bounded redesign and reapplication for a remediable failure, with gate requirements unchanged, no production authorisation meanwhile, and the 0A-only fallback retained.
  • G-1.4 (rq-0-74) TRL 4-5 may release reversible 0A funding tranches. A scout or pathfinder PDR is a separate gate requiring TRL 6 for flight-critical technology.
  • G-1.5 (rq-0-73) T11 (rendezvous scouts) and T18 (sampling and assay) at TRL 6 at scout PDR.
  • G-1.6 (rq-0-69) The month-180 sunset acts automatically; it is not only a prompt for review.
  • G-1.7 (rq-0-67) Any cost above Earth supply needs a separate, explicit owner authorisation; D-01's purpose does not authorise a premium by itself.
  • G-1.8 (rq-0-66) No blanket duplicate TRL 6 demonstration for T11, T18, T09, T12 and T20 at KDP-0B; applicable 0A evidence is reused.

Awaiting evidence

Retired gates (March 2026, 5)

The earlier plan had five numbered gates at fixed months. D-02 replaced them; each is listed with what took its place.

gate-1 Microgravity Materials Processing Viability (month 36)

A 100 g ISS experiment cannot retire the metallurgy risk (scale gap 4–6 orders of magnitude), and whether gravity is needed at all is contested. Metallurgy is now judged per route: route evidence at the 0A mid-term review (mtr-metallurgy) and one complete route at TRL 6 for KDP-0B (kdp-0b-route). Solar-grade Si is deferred.

Replaced by kdp-0b, 0a-mtr
gate-2 Cryogenic Propellant Architecture Selection (month 30)

The cryogenic depot was removed from Phase 0 (round-2 §2); the cryocooler, sunshield and MLI rows move to Phase 1. Tug propellant is selected at the 0A mid-term review (mtr-propellant) under D-05.

Replaced by 0a-mtr
gate-3 ISRU Water Extraction Rate Validation (month 48)

Water extraction is a pilot only if the target is C-type (D-05); industrial electrolysis is deferred to 0B.

Replaced by g-water-pilot, kdp-0b
gate-4 Asteroid Target Selection (month 24)

Target selection now requires sampled recoverable Fe-Ni grade, not a remote survey, and comes after the scouts return data.

Replaced by g-target
gate-5 Phase 0 Preliminary Design Review (month 60)

D-02 replaces the month-60 PDR with KDP-0B, the one-way decision (TRL 6 in a relevant environment, no waivers, for project-ending technologies), and the 0A mid-term review as the internal milestone.

Replaced by kdp-0b, 0a-mtr

Project Dyson — A volunteer-led nonprofit. All plans and research are publicly available.