Phase 0B delivered cost per kg versus Earth supply
Background
The panel does not agree whether 0B material beats Earth supply. Claude: $1,300–11,000/kg (after correcting a round-1 units error), "about as likely as not (33–66%)" to beat Earth supply. GPT: "millions of dollars per kilogram", which the rapporteur shows is inconsistent with GPT's own envelope ($3,000–20,000/kg). Claude and GPT both dispute rq-0-28's finding that Phase 0 costs are "approximately correct".
Raised by the Phase 0 re-assessment (round 2, 2026-10-12): reconciliation/phase-0/round-2/reconciliation/phase.md and reconciliation/phase-0/decisions.md.
Why This Matters
This is the economics gate of D-02 and decides the honest framing of 0B (D-01).
How this gets answered
- Analysis — A delivered-cost model with explicit ranges and a single cost basis, fed by rq-0-50, 0-51, 0-57 and 0-58; multiverse analysis across defensible assumptions.
Research Directions
- $/kg at the node with uncertainty.
- Break-even launch price.
- Reconcile with rq-0-28 and rq-0-43.
Results so far (2026-10-25): chain closure model
A Monte Carlo model follows the chain the regenerated consensus describes: plant output → tug cycles (cycle time and Δv per leg from the rq-0-52 catalogue screen) → fleet → propellant → imported and launched mass → 0B cost → $/kg delivered to SEL1. It compares against shipping the same mass from Earth at the same launch price, plus 20–25% contingency (Claude's DEL-007 rule). Lines not recomputed come from the consensus envelopes in src/lib/data/phase-0-bom.json. Assumptions that are not in any consensus document (commissioning time, site-power mass, spares mass, Earth material cost) are listed in the results file. Code: publications/scripts/phase0_chain_model.py; results: publications/data/phase0-chain/results.json.
| Case (P50) | Tugs | Iodine t/yr | Import ratio | Launch kt | Delivered kt | $/kg delivered | × Earth |
|---|---|---|---|---|---|---|---|
| Reference: catalogue legs ≤6.5 km/s, ≤4-yr cycle, 1.0–1.3 kt/yr, 6–6.5 yr run | 19 | 663 | 0.66 | 6.4 | 3.6 | 21,400 | 5.1 |
| Consensus budgets as written (5 km/s legs, 3-yr cycle) | 18 | 505 | 0.51 | 5.3 | 3.7 | 18,600 | 4.4 |
| Isp 3,000–3,500 s | 19 | 478 | 0.48 | 5.1 | 3.6 | 19,400 | 4.6 |
| 2.3–2.7 kt/yr | 39 | 1,407 | 0.62 | 12.5 | 7.8 | 16,500 | 3.9 |
| Run 15 years | 19 | 663 | 0.66 | 13.0 | 13.7 | 8,700 | 2.1 |
| Run 20 years, Isp 3,000–3,500 s, 2.3–2.7 kt/yr | 39 | 1,002 | 0.45 | 25.2 | 42.2 | 4,900 | 1.2 |
$/kg is 0B only, with 0B contingency at 65%. Earth supply is about $4,300/kg at P50.
What the model shows:
- At the planned scale and run, 0B launches more mass than it delivers. About 6.4 kt goes up to deliver 3.6 kt, and 70% of the launched mass is propellant. No launch price makes 0B cheaper than Earth supply in that case: lowering the price helps the Earth option at least as much. This is the D-01 framing in numbers: Phase 0 at this scale is a capability programme.
- Propellant is about twice the consensus planning figure. The consensus carries 230–400 t/yr. The legs the catalogue supports (5.6–6.5 km/s) give 520–860 t/yr. The import-ratio limit proposed for the gates (≤0.50 interim, ≤0.35 target) fails in 97% of reference draws. Isp of 3,000–3,500 s brings it to about 0.48.
- What would close it is run length and scale, not cheaper launch. The hardware is a one-off and the propellant is not, so cost per kilogram falls with years of operation. Parity with Earth supply needs roughly 20 years at 2.5 kt/yr with Isp above 3,000 s (P50 1.2× Earth; 16% of draws beat it), well beyond the 6–6.5-year 0B the consensus prices.
- The biggest levers on $/kg (rank correlation) are launch price (+0.51), cycle time (+0.42), tug payload (−0.31) and Isp (−0.21).
Limits: tug, plant and robot replacement over long runs is not modelled, which flatters the 15–20-year cases. Gravity assists (rq-0-52) would lower Δv and propellant. Product value at SEL1 beyond its mass (for example avoided Earth-departure constraints) is not credited.
Second pass (2026-11-12): optimised trajectories and replacements
Code: publications/scripts/phase0_chain_model.py (trajectory='optimised', replacements=True), run_phase0_chain_v2.py. Data: publications/data/phase0-chain/results-v2.json.
Two things changed. Tug cycles now come from the optimised low-thrust legs of rq-0-52, each re-checked against the thrust of the tug being modelled. Runs longer than the hardware's service life now buy replacements: tugs and plant modules after 10–15 years, robots at 0.3–0.7 a year beyond the first six.
Cost against Earth supply (P50 ratio, 1.0–1.3 kt a year, with replacements):
| Trajectory setting | Targets | Import ratio | 6.25 yr | 10 yr | 15 yr | 20 yr |
|---|---|---|---|---|---|---|
| No flyby, legs ≤ 6.5 km/s | 16 | 0.58 | 5.2× | 2.8× | 2.1× | 1.9× |
| Lunar flyby 1.0 km/s, legs ≤ 5.0 km/s | 20 | 0.43 | 4.7× | 2.5× | 1.8× | 1.6× |
| Lunar flyby 1.0 km/s, legs ≤ 6.5 km/s | 58 | 0.52 | 5.0× | 2.7× | 2.0× | 1.8× |
| Lunar flyby 1.5 km/s, legs ≤ 5.0 km/s | 45 | 0.41 | 4.6× | 2.4× | 1.8× | 1.6× |
What it shows:
- The cost ratio barely moves at the planned scale. About five times Earth supply for a six-year run, as in the first pass. Hardware and ground cost dominate, not trajectories.
- Lunar flybys fix the import ratio, not the cost. With flybys and the 5 km/s cap, propellant falls to about 420 t a year and the import ratio to 0.41–0.43, inside the ≤ 0.50 limit. Without flybys it is 0.58.
- Replacements take back part of the long-run gain. At 20 years they cost about $9B and raise the ratio from 1.55× to 1.8×. The first pass's "within about 20% of Earth" for a long, large run becomes 1.45× (2.3–2.7 kt a year, 20 years) and 1.3× at 5 kt a year. Asteroid supply beats Earth supply in at most 12% of draws in any case run.
- Picking a fast target helps modestly. Sampling only the fastest quarter of targets lowers the six-year ratio from 4.7–5.0× to 3.9–4.1×.
Tug sizing trade (lunar flyby 1.0 km/s, legs ≤ 6.5 km/s, 10-year run; cells are targets that close / cost ratio / import ratio):
| Tug power | Isp 2,500 s, 150 t payload | Isp 2,500 s, 300 t | Isp 3,250 s, 150 t | Isp 3,250 s, 300 t |
|---|---|---|---|---|
| 0.75 MW | 49 / 2.7× / 0.52 | 21 / 2.1× / 0.37 | 39 / 2.4× / 0.38 | 12 / 1.9× / 0.27 |
| 1.0 MW | 56 / 2.8× / 0.55 | 39 / 2.2× / 0.43 | 53 / 2.5× / 0.41 | 24 / 2.0× / 0.30 |
| 1.5 MW | 58 / 3.1× / 0.59 | 54 / 2.4× / 0.48 | 58 / 2.8× / 0.45 | 48 / 2.2× / 0.35 |
| 3.0 MW | 58 / 3.9× / 0.71 | 58 / 2.8× / 0.54 | 58 / 3.5× / 0.53 | 58 / 2.5× / 0.40 |
- More tug power does not buy a shorter cycle. Cycle time stays at 3.5–3.8 years across a fourfold range of power, because it is set by orbital phasing, not by thrust. Extra power only adds tug mass and cost.
- Payload per trip is the strongest lever on cost, and it trades against target choice. Going from 150 t to 300 t per trip cuts the ratio by about a fifth, but a heavier tug can fly fewer legs: at 1.0 MW and 3,250 s, 300 t leaves 24 targets where 150 t leaves 53.
- Higher Isp helps on both counts (cost and import ratio) and costs targets through lower thrust.
This gives a position on the tug question (plan item 1.3): keep the 5 km/s leg cap and plan on lunar flybys; allow 4-year cycles; do not raise tug power above about 1.5 MW; push payload per trip towards 250–300 t and Isp towards 3,000 s or more, to the extent the candidate count stays above 20. It should be revisited if the flyby gain turns out lower than 1.0 km/s, or if the metal-bearing targets turn out to be among those a heavier tug cannot reach.
Limits of this pass:
- It inherits the limits of rq-0-52, above all the unsourced lunar-flyby gain.
- A leg that the study's tug could not fly is never added back for a more powerful tug, so the benefit of more power is understated in target count (not in cycle time for the targets shown).
- 55% of tug mass and cost is assumed to scale with power; replacement lives and fractions are assumptions listed in the results file.
- Repeat departure windows are not enforced: the fleet is sized from average cycle time.
Flyby assumption checked (2026-11-13)
The lunar-flyby gain these results rest on has been checked against the literature (rq-0-52, research/analysis.md). The size holds at about 1.4 km/s. The 30 days allowed per assisted leg does not; the sources need 60–200.
- Cost and import ratio do not depend on the allowance. At 90 days per assisted leg and four-year cycles the import ratio is 0.42–0.43 and a 20-year run costs 1.6× Earth supply, as before.
- The target count does. At 5 km/s per leg and four years it falls from 20–45 to 12–28, and to 5–16 once the flyby direction is limited to 30° from the ecliptic.
- Five-year cycles restore the count but cost more. 51–83 targets close, the fleet grows by three or four tugs, the six-year run rises from about 4.6× to 5.6–5.9× and the 20-year run from 1.6× to 1.75–1.8×. The import ratio stays at 0.42–0.44.
So the position recorded above (5 km/s cap, lunar flybys, four-year cycles) holds on cost and import ratio but leaves too few targets. The trade is now between a 6.5 km/s leg cap (import ratio about 0.48–0.51) and five-year cycles (more tugs). Results are in publications/data/phase0-chain/flyby-allowance.json.
Re-run on the three-body flyby legs (2026-11-13)
rq-0-52 now takes the flyby from a three-body model of the SEL1 node, the Moon and the escape, with the node burn counted in the leg Δv and the cycle timed node to node. Median results at 1.0–1.3 kt a year, with replacements:
| Leg Δv cap, cycle limit | Targets | Cycle | Import ratio | P(ratio ≤ 0.5) | 6.25 yr | 10 yr | 20 yr |
|---|---|---|---|---|---|---|---|
| 5.0 km/s, 4 yr | 26 | 3.7 yr | 0.46 | 0.69 | 4.9× | 2.6× | 1.7× |
| 5.0 km/s, 5 yr | 67 | 4.3 yr | 0.47 | 0.64 | 5.8× | 2.8× | 1.8× |
| 5.75 km/s, 4 yr | 39 | 3.6 yr | 0.52 | 0.44 | 4.9× | 2.6× | 1.8× |
| 6.5 km/s, 4 yr | 53 | 3.6 yr | 0.55 | 0.32 | 5.1× | 2.7× | 1.9× |
The position recorded in the second pass stands with one change in its basis: the 5 km/s leg cap with lunar flybys and four-year cycles closes on 26 targets, keeps the import ratio at 0.46 and costs the same as before. Raising the cap to 6.5 km/s doubles the targets but takes the import ratio over the 0.50 limit. Five-year cycles are the cheaper way to more targets on import ratio, and the dearer one on cost for a short run. Results are in publications/data/phase0-chain/flyby-model.json.
Re-run with halo node orbits and the inclined Moon (2026-11-15)
rq-0-52's fourth pass puts the node on a halo orbit and the Moon on its tilted orbit. The chain model was re-run on those legs (run_phase0_chain_flyby.py --model=halo). At 5 km/s legs and four-year cycles, with node burns up to 300 m/s:
| Flyby model | Targets | Cycle | Import ratio | 6.25 yr | 10 yr | 20 yr |
|---|---|---|---|---|---|---|
| Third pass (planar orbits, Moon in the ecliptic) | 26 | 3.65 yr | 0.46 | 4.9× | 2.55× | 1.70× |
| Planar orbits, tilted Moon | 25 | 3.65 yr | 0.46 | 4.9× | 2.55× | 1.70× |
| Halo orbits, tilted Moon | 23 | 3.65 yr | 0.45 | 4.9× | 2.54× | 1.69× |
The position stands unchanged. What the halo orbit changes is the node burn: with 150 m/s only, 13 targets close instead of 23, at the same cost ratios. Results: publications/data/phase0-chain/flyby-3d-{planar-orbits,halo}.json.
Re-run with the station at one place on one node orbit (2026-11-16)
rq-0-52's fifth pass requires the tug to leave from, and return to, the place the station is at on the day. Far fewer targets then close at 5 km/s legs and four-year cycles. The chain model was re-run on the best and the worst case (run_phase0_chain_flyby.py --model=station-<orbit> --phase0=k), node burns up to 300 m/s:
| Station | Targets | Cycle | Import ratio | 6.25 yr | 10 yr | 20 yr |
|---|---|---|---|---|---|---|
| Halo 120,000 km, first place | 9 | 3.61 yr | 0.47 | 4.9× | 2.57× | 1.72× |
| Halo 300,000 km, fourth place | 5 | 3.93 yr | 0.46 | 5.2× | 2.64× | 1.74× |
The cost position stands: the chain needs only a few good targets, and those that remain have much the same cycle and Δv. What does not stand is the margin on target count, which rq-0-52 now puts between about 9 and 23 against a falsifier of 20. Results: publications/data/phase0-chain/flyby-station-{halo-120-p0,halo-300-p3}.json.
Target count solved directly (2026-11-18)
rq-0-52 has now solved the tug legs directly instead of reading them from reach tables. At 5 km/s legs and four-year cycles the count is at most 15, even with the station's place free, which is short of the falsifier of 20. With one station it is 17–27 at 6.5 km/s legs, and 26–34 at five-year cycles. The median cycle with one station at five years is 4.4 years, close to the 4.3 years of the five-year row above (5.8× at 6.25 years, import ratio 0.47).
So the trade recorded above is now the one that decides the target count. Five-year cycles are proposed in rq-0-52, because they keep the import ratio under 0.50.
Chain model on the directly solved legs (2026-11-19). The directly solved legs were written in the chain model's leg layout for each of the eight station places (run_phase0_chain_direct.py). The Δv includes the excess speed the node leg could not deliver, charged to the thrusters. The node dates are the ones the direct solve found, and the thrust fraction is scaled up for the extra Δv. The chain was then run at 5 km/s legs, with node burns up to 300 m/s, at five-year cycles and, for comparison, four-year cycles. Ranges are over the eight station places, at 1.0–1.3 kt a year with replacements:
| One station, 5 km/s legs | Targets | Cycle | Fleet | Import ratio | P(ratio ≤ 0.5) | 6.25 yr | 10 yr | 20 yr |
|---|---|---|---|---|---|---|---|---|
| Five-year cycles | 26–34 | 4.3–4.4 yr | 24–25 | 0.44–0.46 | 0.66–0.74 | 5.9–6.2× | 2.84–2.90× | 1.82–1.86× |
| Four-year cycles | 3–7 | 3.1–3.9 yr | 19–22 | 0.41–0.46 | 0.67–0.81 | 4.5–5.3× | 2.43–2.70× | 1.63–1.77× |
| Five-year cycles, table legs (halo, 2026-11-15 legs) | 58 | 4.3 yr | 0.46 | 0.66 |
What this settles:
- The proposed position holds on import ratio. Five-year cycles with one station keep the import ratio at 0.44–0.46, under the 0.50 limit, with 26–34 targets. That clears the falsifier of 20 at every station place.
- What it costs is time and tugs, not import ratio. The fleet grows from about 20 tugs to 24–25. The cost relative to Earth supply rises by about a fifth for a 6.25-year run (6.0× against 4.8× at the median place), and by less over longer runs (2.86× against 2.50× at 10 years, 1.84× against 1.67× at 20).
- The four-year cycles are cheaper but have too few targets (3–7). The cost position of the earlier sections does not change: on the directly solved legs the chain still needs only a few good targets.
- The directly solved legs match the table legs on import ratio and cycle. They lose about half the targets, but the cycle (4.4 years) and the import ratio barely move.
Results: publications/data/phase0-chain/direct-halo-120-c5-y5.json; leg files publications/data/nea-trajectories/legs-direct-halo-120-p{0..7}-c5-y5.csv.
Next steps
- Enforce repeat departure windows in fleet sizing, using the third-pass legs.
- Enforce repeat departure windows per target when sizing the fleet.
- Put the import ratio and the launched-to-delivered mass ratio into the economics gate (rq-0-82), alongside $/kg.
- Re-run the bom-0-4 and bom-0-16 consensus with these findings.
Question Details
- Source Phase
- Phase 0 - Resource Acquisition
- Source BOM Item
- Material Processing Station
- Question ID
- rq-0-61
- Created
- 2026-10-12
- Related BOM Items
- bom-0-3bom-0-4bom-0-2