Validation Roadmap

Experiments and missions mapped to open research questions and BOM specifications. Track validation activities that will de-risk Project Dyson engineering decisions.

Validation Timeline

20262027202820292030Propulsion Technology Val...Collector Unit Material S...ISRU Technology ReadinessSwarm Coordination Archit...KDP-0A: authorise bounded...Ground-based Xenon Hal...ISS PV Degradation Stu...Iodine Hall Thruster F...LEO Membrane Deploymen...Multi-Satellite Swarm ...Perovskite PV Space Qu...ISRU Demonstrator Miss...Dense Constellation Co...Asteroid Redirect Demo
Proposed
Funded
In Progress
Completed
Cancelled
Critical Milestone

Roadmap Overview

9
Total Experiments
$1.4B
Total Est. Cost
17
RQs Addressed

By Status

Proposed 3
Funded 3
In Progress 3

By Year

2026 3
2027 3
2028 2
2030 1
BOM Items Validated 9
Showing 9 experiments
2026
In Progress

Ground-based Xenon Hall Thruster Tests

NASA Glenn Research Center

Comprehensive ground testing campaign for high-power (10-20 kW) Hall thrusters using xenon propellant. Tests include lifetime validation, performance characterization, and erosion measurements to validate transport vehicle propulsion specifications.

propulsionhall-thrusterxenonground-test
$15M
2 RQs 1 BOM
Feeds T01

Xenon module evidence for T01 (panel: Xe branch TRL 3–4). The MW-class cluster must reach TRL 6 before KDP-0B (D-02); 10–20 kW tests do not close that gap alone (rq-0-79).

Learn more
2027
Funded

LEO Membrane Deployment Test

NASA/L'Garde Partnership

Orbital demonstration of large-area thin-film membrane deployment mechanisms in LEO. Tests deployment reliability, membrane tension control, and structural dynamics for collector unit design validation.

deploymentmembranestructuralLEO
$45M
3 RQs 2 BOM
Learn more
2028
Funded

ISRU Demonstrator Mission

NASA Artemis Program

Lunar surface demonstration of in-situ resource utilization for oxygen extraction and regolith processing. Validates mining robot operational concepts and material processing specifications for Phase 1 manufacturing expansion.

isrulunarminingoxygen-extraction
$350M
4 RQs 3 BOM
Feeds T04T18

Regolith-contact and sampling evidence toward TRL 4–5 for the 0A mid-term review and the target gate (D-02).

Learn more
2026
In Progress

ISS PV Degradation Study

NASA Johnson Space Center

Ongoing analysis of International Space Station solar array performance data spanning 25+ years. Provides long-baseline radiation damage and degradation data for validating collector unit lifetime models.

solar-arraysdegradationradiationlong-duration
$2M
3 RQs 2 BOM
Feeds T02T15

Degradation data for MW-scale arrays, which must reach TRL 6 before KDP-0B (D-02).

Learn more
2030
Proposed

Asteroid Redirect Demo

NASA/ESA Joint Mission

Technology demonstration for asteroid capture and redirect techniques applicable to Near-Earth Object mining operations. Validates capture system designs and low-thrust trajectory optimization for material transport.

asteroidcaptureredirection-propulsion
$800M
3 RQs 2 BOM
Feeds T11T12

Rendezvous and heavy-handling evidence; scouts need TRL 6 at their PDR (G-1.5).

2027
Funded

Multi-Satellite Swarm Coordination Testbed

MIT Space Systems Laboratory

Ground-based hardware-in-the-loop simulation facility for testing swarm coordination algorithms at scale. Validates distributed control architectures and inter-satellite communication protocols for million-unit swarm management.

swarmcoordinationsimulationdistributed-systems
$25M
3 RQs 1 BOM
Learn more
2027
Proposed

Perovskite PV Space Qualification

NREL/NASA Partnership

Dedicated space experiment to qualify perovskite solar cells for long-duration space applications. Tests radiation tolerance, thermal cycling stability, and encapsulation effectiveness in the GEO radiation environment.

perovskitesolar-cellsradiationqualification
$35M
2 RQs 2 BOM
Learn more
2026
In Progress

Iodine Hall Thruster Flight Demonstration

Busek/ThrustMe

Orbital demonstration of iodine-fueled Hall thrusters as xenon alternative. Tests long-duration performance, storage system reliability, and feed system behavior to validate alternative propellant strategies.

propulsioniodinehall-thrusteralternative-propellant
$18M
2 RQs 1 BOM
Feeds T01T14

Iodine branch evidence for T01 and T14 (panel: I₂ TRL 2–3); a small iodine flight does not validate MW scaling (rq-0-79).

Learn more
2028
Proposed

Dense Constellation Collision Avoidance Demo

ESA/Starlink Collaboration

Operational demonstration of autonomous collision avoidance in a dense satellite constellation. Tests real-time maneuver planning, inter-satellite coordination, and ground segment integration for swarm safety validation.

collision-avoidanceconstellationsafetyautonomous
$120M
2 RQs 2 BOM
Learn more

About the Validation Roadmap

Purpose

The validation roadmap maps open research questions to specific experiments and missions that can resolve them. This helps prioritize validation activities and track progress toward engineering confidence.

Experiment Types

Experiments include ground-based testing, orbital demonstrations, and analysis of existing mission data. Each experiment is linked to the research questions and BOM items it validates.

Timeline

The timeline shows when validation data is expected. Critical milestones indicate decision points where validated specifications enable phase transitions.

Project Dyson — A volunteer-led nonprofit. All plans and research are publicly available.